Warsaw-Radom Airport (expansion of the Radom-Sadków airport)
In 2018, Polskie Porty Lotnicze took over the failing Radom-Sadków airport (for PLN 12.7 million) and rebuilt it into the Warsaw-Radom airport. Construction began in May 2019; the new terminal, with a capacity of 3 million passengers per year, was commissioned on 27 August 2022, and the first passenger operation took place on 27 April 2023. The cost of the investment rose from the planned approximately PLN 425 million to nearly PLN 800 million, although the airport was originally to have been ready as early as 2020. Traffic remains many times lower than capacity – over the whole of 2025 the airport handled 95,000 passengers – and since 28 November 2025 the Regional Prosecutor's Office in Lublin has been conducting an investigation into the expenditure on the expansion of an amount indicated by PPL as damage of no less than PLN 812.5 million.
How it went
Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. How to read this section
Timeline
Slip: about 2 years vs. the original date (given as a year)
Change history
- 27 Apr 2023stage: operational
- 27 Aug 2022stage: commissioning
- May 2019stage: construction
Significance
The terminal was prepared to receive 3 million passengers per year, but actual traffic is many times lower: 95,000 passengers over the whole of 2025, while a record June 2026 brought 16,100 travellers (approximately 22 percent more year on year). PPL subsidises the airport by tens of millions of złoty per year, and the current PPL president Andrzej Ilków assessed that this infrastructure should have been built in Modlin, and deemed the decision to build in Radom a mistake. The company filed a notification with the prosecutor's office against former management boards, indicating damage of no less than PLN 812.5 million; scenarios for changing the airport's role, including a takeover by the military, are being publicly considered. The project functions in public debate as a flagship example of a misguided public mega-investment.
Sources 12 · 9 independent · 9 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- [1]Za 800 mln zł zbudowali nowe lotnisko w Radomiu. Będzie potrzebować dekad, żeby stać się rentownym portem ↗archived ✓Money.pl4 Sep 2022CostAnnouncedConstruction startLast stated dateBudget
Cost · BudgetBudżet zamyka się na poziomie blisko 800 mln zł. Kwota ta uwzględnia już wszystkie przetargi, wprowadzone zmiany w projektach i aneksy do umów
AnnouncedPrzedsiębiorstwo Państwowe "Porty Lotnicze" (PPL) w 2018 r. kupiło upadające lotnisko Radom-Sadków za kwotę 12,7 mln zł.
Construction startWbicie pierwszej łopaty na budowie nowego lotniska w Radomiu w maju 2019 r.
Last stated dateOtwarcie lotniska Warszawa-Radom planowane jest na kwiecień 2023 r.
LocationPierwszą łopatę pod budowę nowego lotniska w Radomiu w maju 2019 r. wkopali premier Mateusz Morawiecki, wicemarszałek Senatu Adam Bielan, poseł PiS Marek Suski, Mikołaj Wild (ówczesny pełnomocnik rządu ds. CPK) i Mariusz Szpikowski (ówczesny prezes PPL)
- Pasazer.com30 Sep 2022FundingUtilisation
FundingPrzychody i koszty finansowe zostały pominięte z powodu ich marginalnego znaczenia, bowiem PPL realizuje radomską inwestycję ze środków własnych.
FundingW sumie wsparcie samorządu wyniesie 270 mln zł.
UtilisationPierwsza miała polegać na rozbudowie lotniska do przepustowości 3 mln pasażerów rocznie i kosztować 425 mln zł.
- OKO.press27 Apr 2023
- Money.pl12 Sep 2024
- Money.pl5 Nov 2025StatusOriginal dateDeliverySchedule
Status · DeliveryPort lotniczy Warszawa-Radom został uroczyście otwarty 27 kwietnia 2023 r.
Original date · SchedulePrzypomina, że pierwotnie lotnisko miało być gotowe nawet w 2020 r., a brak dotrzymania tego terminu wskazano jako jedno z ryzyk.
- Forsal.pl5 May 2026
- Wikipedia (pl)DeliveryStage history
DeliveryPierwsza operacja pasażerska miała miejsce 27 kwietnia 2023, kiedy to o 22:00 wylądował lecący z Paryża Boeing 737 MAX 8 linii LOT
Stage history27 sierpnia 2022 operator oddał do użytku nowy terminal mogący obsłużyć 3 mln pasażerów rocznie
- Polskie Porty Lotnicze S.A.Investor
InvestorPolskie Porty Lotnicze Spółka Akcyjna (dawniej Przedsiębiorstwo Państwowe "Porty Lotnicze") przejęły lotnisko w Radomiu
- TransInfo.pl2 Jul 2026Stage
StageW pierwszym miesiącu wakacji z oferty radomskiego portu skorzystało ponad 16,1 tys. pasażerów
- XYZ.pl21 Mar 2025Budget
BudgetKoszty oszacowano na 425 mln zł. Okazało się jednak, że faktyczne koszty były co najmniej dwukrotnie wyższe.
- Rynek Lotniczy9 Jan 2026Utilisation
UtilisationZ danych przekazanych przez PPL wynika, że ubiegły rok zakończył się dla Lotniska Warszawa-Radom wynikiem 95 646 obsłużonych pasażerów
- WNP.pl12 Dec 2025Losses
LossesProkuratura sprawdza, czy podejmowane przez władze spółki decyzje spowodowały szkodę majątkową w PPL w kwocie co najmniej 812,5 mln zł.