Łódź Regional Tramway (ŁTR)

completedstage: operationaldeliveredrescaled
PLN 281 million
estimate · data from 2008net or gross: not recorded≈ PLN 281 million (value-by-stage, est., nominal)funding: EU funds, local governmentLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Łódź Regional Tramway (ŁTR) was a project, carried out in 2007–2008, to modernise the north-south fast-tram trunk line in Łódź, originally intended to connect Łódź with Zgierz (to the north) and with Ksawerów and Pabianice (to the south). Stage I was carried out from 7 July 2007 and finished on 30 June 2008, with the route opened for use on 1 July 2008. What was completed at that time was the section within the administrative boundaries of Łódź, from the Helenówek depot to Chocianowice (around 28.9 km), including new stops, track, traction substations and a traffic-control system, together with the purchase of new rolling stock. Stage I (the Łódź section) cost PLN 281 million, including a PLN 103 million grant from the European Regional Development Fund; the total planned cost of the whole project (including the sections to Zgierz and Pabianice) was PLN 442,018,200. The beneficiary and operator was MPK-Łódź, with support from the City of Łódź. The Łódź Regional Tramway was carried out only between Helenówek and Chocianowice. The new trams never ran to Pabianice, and on 2 November 2009 the town of Zgierz withdrew from building its section because the grant on offer was too low; the renovated route to Zgierz did not open until December 2021.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[1]
Scoperescaled down[3]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

eksploatacja magistrali szybkiego tramwaju
Current
trasa Helenówek–Chocianowice czynna i eksploatowana od 1 lipca 2008 r.

Timeline

  1. Construction start7 Jul 2007
  2. Delivery1 Jul 2008

Significance

The Łódź Regional Tramway was the largest tram project in the Łódź metropolitan area and one of the first ventures in Poland to build a fast tram line with a regional character, co-financed from European Union funds. It modernised Łódź's north-south tram trunk line (Helenówek–Chocianowice), including the track, stops, substations and new rolling stock. The project's intended regional scope was not fully realised, however: the connection to Pabianice was never built, and the section to Zgierz was not opened until December 2021, as a separate undertaking.

Sources 5 · 3 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusCostConstruction startDeliveryFundingUtilisation
    Status · Delivery1 lipca 2008 roku – oddanie do użytkowania trasy Łódzkiego Tramwaju Regionalnego
    Cost · Fundingetap I (łódzki) kosztował 281 mln zł (w tym: dotacja unijna – 103 mln zł)
    Construction startRealizacja I etapu rozpoczęła się 7 lipca 2007 r.
    Utilisation1 lipca 2008 roku – oddanie do użytkowania trasy Łódzkiego Tramwaju Regionalnego, pierwszy dzień kursowania wagonów Pesy na trasie Zajezdnia Helenówek – Chocianowice.
  2. Rynek Kolejowy18 Aug 2006
    InvestorFunding
    InvestorMiejski przewoźnik jako beneficjent musi organizować i prowadzić przetargi, zawierać kontrakty na wykonanie, a później monitorować postępy prac.
    FundingResztę pieniędzy wyłoży MPK z pomocą miasta.
  3. Wikipedia (pl)
    StageScope
    StageŁódzki Tramwaj Regionalny został jednak wykonany tylko między Helenówkiem a Chocianowicami
    Scopenowe tramwaje nie kursowały do Pabianic
  4. wnp.pl (Portal gospodarczy WNP.PL)11 Mar 2016
    Status
    StatusW Łodzi w poprzednich latach największymi inwestycjami tramwajowymi była modernizacja w latach 2007-2008 trasy północ-południe z Helenówka do Chocianowic (Łódzki Tramwaj Regionalny) oraz modernizacja i przedłużenie w latach 2013-2015 trasy WZ Retkinia - Olechów (unijny projekt za ponad 742 mln zł, w tym 450 mln zł z UE).
  5. Instytut Spraw Obywatelskich (INSPRO)16 Jan 2024
    Status
    StatusNowa ekipa postawiła na modernizację ciągu transportowego północ-południe, czego konsekwencją był realizowany w latach 2007–2008 Łódzki Tramwaj Regionalny. W założeniach miał połączyć Zgierz, Łódź i Pabianice, w praktyce środki unijne na remonty torów i zakup dziesięciu nowoczesnych tramwajów trafiły jedynie do Łodzi.