Internet for Masovia (Regional Broadband Network of the Masovian Voivodeship)
Internet for Masovia (IDM) is a project to build a regional backbone-and-distribution fibre-optic network, carried out by the Self-Government of the Masovian Voivodeship, aimed at eliminating the so-called 'white spots' and providing access to fast internet for residents and public institutions across the voivodeship. The contract engineer was Agencja Rozwoju Mazowsza S.A. (Masovia Development Agency). On 3 October 2013 a contract for the network's construction was signed with a Polish-Korean consortium led by the Korean company KT Corporation, with members including Daewoo International Corporation, Asseco Poland, Warszawskie Przedsiębiorstwo Robót Telekomunikacyjnych, BIATEL Telekomunikacja, BIATEL BIT and KBTO. The value of the whole undertaking came to about PLN 458 million gross, with an EU grant of over PLN 340 million from the Regional Operational Programme of the Masovian Voivodeship 2007–2013. In total, more than 3,600 km of fibre-optic routes were built (3,680 km under the contract), together with 42 backbone nodes, 4 technical nodes and 308 distribution nodes. The official opening of the Network Management Centre took place on 21 September 2015 in Warsaw; the network is now in its operating phase. The project was described as the largest undertaking of its kind then being carried out in Europe.
How it went
Assessment: settled, as of 21 Sep 2015. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- sieć wybudowana i eksploatowana (faza operatorska), Centrum Zarządzania Siecią otwarte 21 września 2015
Timeline
- Original date2015
- Delivery2015
Significance
The Internet for Masovia project was, at the time, the largest undertaking of its kind in Europe to build a regional broadband network, and a key element in tackling digital exclusion in the Masovian Voivodeship, where a significant number of municipalities lay in areas with limited internet access. The fibre-optic infrastructure built (more than 3,600 km of routes, 42 backbone nodes and 308 distribution nodes) created an open wholesale network enabling telecommunications operators to provide broadband services to the region's residents and public institutions.
Sources 7 · 5 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Agencja Rozwoju Mazowsza S.A. / Samorząd Województwa MazowieckiegoCostDeliveryInvestorFunding
CostWartość całego przedsięwzięcia to około 458 mln zł. Przyznana dotacja unijna wynosi ponad 340 mln zł.
DeliveryOficjalne otwarcie odbyło się 21 września 2015 r. w Warszawie.
InvestorAgencja Rozwoju Mazowsza S.A. jako inżynier kontraktu
FundingPrzyznana dotacja unijna wynosi ponad 340 mln zł.
- Prawo.pl4 Oct 2013
- Bankier.pl2 Oct 2013Cost
Costoferta konsorcjum KT Corporation, Daewoo International Corporation, Asseco Poland, Warszawskie Przedsiębiorstwo Robót Telekomunikacyjnych, Biatel Telekomunikacja, Biatel BIT, KBTO za około 458 mln zł brutto
- PortalSamorzadowy.pl7 Apr 2014Original date
Original dateDo końca 2015 r. w woj. mazowieckim wybudowana zostanie sieć światłowodowa o długości 3680 km.
- Agencja Rozwoju Mazowsza S.A.StatusStageUtilisation
Status · Stage · UtilisationSTATUS REALIZACJI PROJEKTU Internet dla Mazowsza znajduje się w fazie operatorskiej.
- Funding
FundingDofinansowanie unijne wynosi 85%, 15% to środki Samorządu Województwa Mazowieckiego.