HVO plant in Płock (hydrotreatment of vegetable oils)

completedstage: operationaldelivered
PLN 800 million
programme budget (multi-year) · data from May 2026net or gross: not recorded≈ PLN 800 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A new plant for the hydrotreatment of vegetable oils (HVO) at the ORLEN production facility in Płock, commissioned on 25 May 2026. Its capacity is approximately 300 thousand tonnes of biocomponents per year, produced from feedstocks including rapeseed oil and used cooking oil (UCO). The value of the investment exceeded PLN 800 million. Commissioning the plant increases the ORLEN Group's total biofuel production potential to approximately 700 thousand tonnes per year, with an announced increase to 1.1 million tonnes by 2030.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote, one has an assessment the record's own timeline contradicts. How to read this section

Deliverydelivered[1]

Timeline

  1. Delivery25 May 2026

Change history

  • May 2026stage: operational

Significance

The plant reduces the ORLEN Group's dependence on imported biocomponents and supports the achievement of transport decarbonization targets – the National Indicative Target (set at 10 percent for 2026) and EU RED III requirements. Production of HVO biofuel from local agricultural and waste feedstocks is intended to lower greenhouse gas emissions by at least 65 percent relative to conventional fuels, while building a domestic value chain based on Polish agriculture.

Sources 7 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. ORLEN S.A.25 May 2026
    StatusStageCostInvestorDelivery
    Status · Stage · Investor · DeliveryKoncern uruchomił w Płocku nowoczesną instalację do uwodornienia olejów roślinnych (HVO) o wydajności ok. 300 tys. ton rocznie.
    CostWarta ponad 800 mln zł instalacja wspiera realizację celów dekarbonizacji transportu
    InvestorORLEN realizuje największy w Polsce program inwestycji w biopaliwa, co zapewni koncernowi dostęp do kluczowych biokomponentów.
    LocationKoncern uruchomił w Płocku nowoczesną instalację do uwodornienia olejów roślinnych (HVO)
  2. Inwestycje.pl26 May 2026
  3. BiznesAlert.pl26 May 2026
  4. ORLEN S.A.May 2026
  5. Hydrocarbon Engineering3 Jun 2026
  6. Bankier.pl30 Sep 2021
  7. Parkiet