HyperPIC — VIGO Photonics photonic integrated circuit factory
HyperPIC (full name: "Photonic integrated circuits for mid-infrared applications") is a flagship Polish project to build domestic capacity for the production of photonic integrated circuits, carried out by the GPW-listed company VIGO Photonics from Ożarów Mazowiecki near Warsaw. Through the project, VIGO is to become the world's first manufacturer of photonic integrated circuits for the mid-infrared (MIRPIC). The project received funding from NCBR under the European Funds for a Modern Economy (FENG) and the IPCEI Microelectronics/Communication Technologies mechanism in the amount of approx. PLN 453.7 million, with eligible costs of approx. PLN 878.6 million. Construction of the new plant, estimated at approx. one billion zlotys, is to begin in early 2027, with the start of series production planned for after 2029. The entire undertaking is scheduled for 2023–2030.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
- Announced 2023
- Original date 2030
- Current date 2030
Change history
- 2023 stage: announced
Significance
The project aims to build in Poland the world's first production chain for photonic integrated circuits for the mid-infrared (MIRPIC), strengthening domestic and European competencies in microelectronics and semiconductors under IPCEI. VIGO Photonics plans to expand its team from the current more than 200 to approx. 450–500 employees by 2030, creating about 300 new, highly specialized jobs, and the technology is to find application in many industrial sectors and consumer electronics.
Sources 5 · 4 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Bankier.pl 29 May 2024cost.fundingInvestor
- Forbes.pl 17 Apr 2025Original datecost.funding
- VIGO Photonics (materiał oficjalny) 2024Statuscost.fundingAnnouncedOriginal dateCurrent date
Status „Realizacja projektu HyperPIC planowana jest w latach 2023-2030"
cost.funding „Rekomendowana kwota dofinansowania w projekcie wynosi 453 694 142,06 zł"
Current date „fazy FID (First Industrial Deployment) tj. pierwszego przemysłowego wdrożenia (lata 2023-2030)"
- Evertiq 17 Apr 2025CostStage
Stage „Budowa zakładu ma ruszyć na początku 2027 r."
Cost „Powstanie nowego zakładu ma kosztować około miliarda zł."
- Investmap.pl 17 Apr 2025InvestorCostStage
Investor „Polska spółka akcyjna VIGO Photonics (do 2022 r. działającej pod nazwą VIGO System) z Ożarowa Mazowieckiego pod Warszawą"
locations „Realizacja inwestycji w Ożarowie Mazowieckim pod Warszawą ma ruszyć na początku 2027 r."