🚆Transportstrategic

Protective Breakwaters of the Outer Port in Gdynia

under construction stage: permits
540 mln PLN
contract value · data from Oct 2024 ≈ 540 mln PLN (value-by-stage, est., nominal) funding: Port of Gdynia Authority

Construction of a new system of protective breakwaters forming the waterside access infrastructure for the planned Outer Port in Gdynia. The design-and-build contract for nearly 2.5 km of breakwaters was signed on 2 October 2024 between the Port of Gdynia Authority and a consortium of Budimex (leader), Roverpol and Rover Maritime. The contract is worth approximately PLN 438.7 million net (approximately PLN 539.6 million gross). The scope of works covers a design stage together with obtaining a building permit (up to 490 days from signing the contract) as well as construction works together with an occupancy permit (up to 819 days from obtaining the building permit). Construction of the breakwaters is scheduled to begin in mid-2026, with completion of all works in the second quarter of 2028.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial
Schedule on time

Timeline

  1. Construction start 2 Oct 2024
  2. Original date 2028
  3. Current date 2028

Change history

  • May 2026 stage: permits

Significance

The protective breakwaters constitute public maritime access infrastructure that is a precondition for the creation of the Outer Port in Gdynia — a key element intended to enable the subsequent construction of the actual pier and the deep-water terminal. The access infrastructure is the responsibility of the maritime administration, and its financing is provided by the Port of Gdynia Authority.

Sources 5 · 4 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Rynek Infrastruktury 2 Oct 2024
    InvestorCurrent date
    Investor „Zarząd Morskiego Portu Gdynia podpisał umowę z konsorcjum Budimeksu, Roverpolu oraz Rover Maritime na zaprojektowanie i wybudowanie nowych falochronów osłonowych."
    Current date „Zakończenie realizacji prac zaplanowano na drugi kwartał 2028 roku."
  2. Budimex S.A. 2 Oct 2024
    Construction startOriginal dateInvestorSignificance
    name.pl „Budowę falochronów osłonowych, stanowiących wodną infrastrukturę dostępową do Portu Zewnętrznego"
    Original date „Prace mają się zakończyć w drugim kwartale 2028 roku."
  3. Money.pl 5 May 2026
    StatusStageStage historySignificance
    Status „Roboty budowlane w zakresie falochronów zostaną rozpoczęte w połowie bieżącego roku"
    Significance „kluczowy element, który umożliwi późniejszą budowę właściwego pirsu"
  4. Zawsze Pomorze 2 Oct 2024
    cost.fundingConstruction start
    Construction start „w środę, 2 października umowę dotyczącą budowy falochronów osłonowych"
    cost.funding „Za infrastrukturę dostępową odpowiedzialny jest urząd morski, finansowanie odbywa się poprzez zarząd Portu Gdynia"
  5. Gdynia.pl (Urząd Miasta Gdyni) Jun 2024
    DescriptionCost
    Cost „438 699 534,11 zł netto (539 600 426,96 zł brutto)"
    Description „prace projektowe wraz z uzyskaniem pozwolenia na budowę, które mają zostać zakończone do 490 dni"