Northvolt battery systems plant in Gdańsk (Northvolt Dwa)

completedstage: operationaldeliveredrestructured
USD 200 million
estimate · data from Nov 2024net or gross: not recorded≈ PLN 800 million (value-by-stage, est., nominal)funding: private finance, EU fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

An energy storage systems (BESS) production plant launched by the Swedish group Northvolt in the Stogi district of Gdańsk, on Andruszkiewicza Street. At the time of its opening in 2023, it was presented as the largest factory of its kind in Europe, with a target capacity of around 6 GWh per year and employment reaching nearly 300 people. Following Northvolt's bankruptcy, production was ended and the facility was taken over by the American company Lyten.

Why it failed

The battery systems plant in Gdańsk fell victim to the financial crisis of the Northvolt group. On 21 November 2024, the company filed for creditor protection under Chapter 11 in the United States, and on 12 March 2025 its bankruptcy was declared in Sweden. Northvolt ended production activity in Gdańsk (announced 22 November 2024, a year and a half after the plant was put into service), and the facility was sold to the American company Lyten – the transaction was finalized in October 2025.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[3]
Utilisationin use[5]
Scoperestructured[6]
operational status relative to target annual production capacity
Current
produkcja wznowiona pod koniec 2025 r.; fabryka działa i została oficjalnie otwarta 20.03.2026 ('pełną parą')
Capacity or target
6 GWh/rok (z możliwością rozbudowy do 12 GWh)
Unit
GWh/yr

Timeline

  1. Announced2021
  2. DeliveryMay 2023

Change history

  • 15 Oct 2025status: completedThe plant (Northvolt Dwa) was taken over by the American company Lyten – the transaction was finalized in October 2025. The new owner resumed production at the end of 2025 and officially opened the factory on 20.03.2026, presenting it as the largest centre for producing battery energy storage systems (BESS) in Europe.
  • 22 Nov 2024status: pausedNorthvolt announced the end of production activity in Gdańsk (22.11.2024). The company filed for creditor protection under Chapter 11 in the USA (21.11.2024), and on 12.03.2025 its bankruptcy was declared in Sweden.
  • May 2023stage: operational

Significance

The plant was to be one of the pillars of the European energy storage supply chain – the largest BESS factory on the continent, with a facility of approx. 25,000 m², a target capacity of up to 6 GWh per year and employment reaching nearly 300 people. The financial collapse of the Northvolt group cut short these plans: some jobs were eliminated, and the plant's strategic potential passed under the control of a foreign investor (Lyten), which announced a resumption of production.

Sources 10 · 8 independent · 8 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Notes from Poland25 Nov 2024
    AnnouncedSignificance
    Announced · SignificanceOne of them, which only opened last year, had been planned as Europe's largest factory for energy storage systems when it was announced in 2021.
  2. Gdansk.pl (Miasto Gdańsk)22 Nov 2024
    StageStage historyInvestorCostSignificanceDelivery
    Stage · Stage history · DeliveryUruchomiono ją w 2023 roku
    InvestorFirma Northvolt ogłosiła w piątek, 22 listopada, zakończenie działalności w Polsce i Szwecji
    CostInwestycja kosztowała około 200 mln dolarów
    Locationfabryki znajdującej się przy ul. Andruszkiewicza w Gdańsku
    SignificanceZatrudniono tu blisko 300 pracowników
  3. Lyten15 Oct 2025
    StatusFailure descriptionSignificanceDelivery
    Status · DeliveryNorthvolt Dwa is a 25,000-square meter (270,000-square foot) battery energy storage system (BESS) manufacturing and R&D facility that was opened in 2023.
    Failure descriptionLyten Completes Acquisition of Northvolt BESS Manufacturing Facility in Poland
    SignificanceNorthvolt Dwa is a 25,000-square meter (270,000-square foot) battery energy storage system (BESS) manufacturing and R&D facility that was opened in 2023. The facility includes equipment to ramp up to 6 GWh of energy storage manufacturing capacity and the ability to expand to up to 12 GWh in the future.
    DeliveryNorthvolt Dwa is a 25,000-square meter (270,000-square foot) battery energy storage system (BESS) manufacturing and R&D facility that was opened in 2023
    Failure descriptionOctober 16, 2025 – (BUSINESS WIRE) – Lyten, the global leader in lithium-sulfur batteries and energy storage, announced today that it has completed its acquisition of Northvolt Dwa in Gdańsk, Poland.
  4. Wikipedia
    Failure description
    Failure descriptionThe company filed Chapter 11 bankruptcy in the United States on November 21, 2024.
    Failure descriptionIt subsequently filed for bankruptcy in Sweden on March 12, 2025.
  5. Gdansk.pl (Miasto Gdańsk)20 Mar 2026
    Utilisation
    UtilisationLyten wznowił produkcję baterii w Gdańsku pod koniec 2025 r.
    Utilisationoficjalnie otworzyła w piątek, 20 marca, zakład produkcyjno-badawczy w Gdańsku.
  6. Energy-Storage.news1 Jul 2025
    Scope
    ScopeWe plan to immediately restart operations in Poland and deliver on existing and new customer orders
  7. Funding
    FundingAMOUNT OF THE INNOVATION FUND GRANT EUR 75 451 457
  8. Funding
    FundingNorthvolt to invest $200 million in Greenfield factory project tooled for assembly of cutting-edge, sustainable energy storage systems.
  9. Green-news.pl24 Aug 2023
    Stage historyDelivery
    Stage history · DeliveryZakład oddano do użytku w maju tego roku, jest największym tego typu w Europie

    year taken from the source's publication date (24 Aug 2023)