The Mercedes-Benz Manufacturing Poland plant in Jawor in Lower Silesia produces four-cylinder gasoline and diesel engines and batteries for Mercedes-Benz passenger cars, including plug-in hybrids and electric vehicles. Construction began in 2017, and production started in 2019. The value of the investment in the engine and battery plant was estimated at around EUR 600 million (over PLN 2.5 billion). It is the first Mercedes-Benz engine production plant outside Germany; it employs over 1,600 people, and in January 2024 its millionth engine was produced.
How it went
Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- 1 000 000 silników benzynowych M254 (milionowy silnik wszystkich typów powstał w styczniu 2024 r.) (by 2025-07-22)
- Unit
- engines
Timeline
- Construction start2017
- Delivery2019
Change history
- 2019stage: operational
- 2017stage: construction
Significance
The plant in Jawor made Poland the first location for Mercedes-Benz engine production outside Germany and integrated Lower Silesia into the group's global supply chain. It created over a thousand highly skilled jobs (ultimately over 1,600), and the engines and batteries produced there go to Mercedes-Benz plants around the world. The plant also became the base for a further investment worth over a billion euros in an electric delivery van factory.
Sources 7 · 7 independent · 6 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Mercedes-Benz Manufacturing PolandStageCostConstruction startDeliveryFunding
Stage · Deliveryproducing engines, engine components, and batteries for hybrid vehicles since 2019
Cost · FundingThe value of Mercedes-Benz AG’s investment in building the engine and battery factory in Jawor is approximately 600 million euros, or over 2.5 billion PLN.
Construction startConstruction began in 2017.
- Invest in Wrocław10 Jul 2026StatusInvestor
Status · InvestorMercedes-Benz Manufacturing Poland in Jawor has been producing engines, engine components and batteries for hybrid cars since 2019
- Mercedes-Benz PolskaJan 2024
- Money.pl22 Jan 2019
Locationw położonym ok. 100 km od granicy z Niemcami Jaworze powstanie kolejny zakład produkcyjny tej firmy
- AutomotiveSuppliers.plJul 2025Utilisation
Utilisation22 lipca 2025 roku fabryka Mercedes-Benz Manufacturing Poland (MBMPL) osiągnęła kolejny kamień milowy. W zakładzie w Jaworze świętowano wyprodukowanie 1 000 000 silnika benzynowego M254 oraz 600 000 skrzyni korbowej do silników diesla OM654.
- Funding
FundingRząd dopłaci do budowy fabryki silników Mercedes-Benz w Jaworze 18,7 mln euro - taką decyzję podjęło Ministerstwo Rozwoju.
Fundingfabryka powstanie na terenie Wałbrzyskiej Specjalnej Strefy Ekonomicznej. Koncern będzie mógł korzystać z ulgi do 2026 roku