PepsiCo (Frito-Lay) plant in Święte near Środa Śląska

completedstage: operationaldelivered
PLN 1.0 billion
programme budget (multi-year) · data from May 2023net or gross: not recorded≈ PLN 1.0 billion (value-by-stage, est., nominal)funding: private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

PepsiCo (Frito Lay sp. z o.o.) built a new snack production plant in the village of Święte in the municipality of Środa Śląska, a dozen or so kilometers from Wrocław. The cornerstone was laid on 26 August 2021, and the factory was officially opened on 31 May 2023. The value of the investment exceeded PLN 1 billion, making it the company's fifth production plant in Poland. The plant produces Lay's chips and – for the first time in Poland – Doritos corn chips, destined for 20 European markets. Target employment was planned at around 450 people. The facility is promoted as PepsiCo's most environmentally sustainable snack plant in Europe, with a goal of climate neutrality by 2035.

How it went

Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[2]
Utilisationin use[2]

Timeline

  1. Construction start26 Aug 2021
  2. Original dateMay 2023
  3. Last stated dateMay 2023
  4. Delivery31 May 2023

Change history

  • 31 May 2023status: completedOfficial opening of the plant in Święte on 31 May 2023.
  • 31 May 2023stage: operational
  • 26 Aug 2021stage: construction

Significance

The plant is one of the largest FMCG-sector investments in Lower Silesia in recent years and PepsiCo's fifth production plant in Poland, described by the investor as PepsiCo's largest investment in the country. It launched production of Lay's chips from Polish potatoes and – for the first time in Poland – Doritos chips, some of which go to 20 European markets, strengthening the region's export role. The investment, worth over PLN 1 billion, ultimately created around 450 jobs (some later reports cite over 600 employed), mainly for residents of the region. The plant is positioned as PepsiCo's most environmentally sustainable snack plant in Europe, with a declared goal of achieving climate neutrality (zero emissions) by 2035.

Sources 6 · 6 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. IEA (Industrial Engineering Agency)2023
  2. Gmina Środa ŚląskaMay 2023
    StatusStageCostDeliveryUtilisation
    Status · Stage · Delivery31 maja oficjalnie otwarto zakład koncernu PEPSICO w Świętem.

    year taken from the source's publication date (May 2023)

    CostKoszt budowy piątego zakładu produkcyjnego koncernu PepsiCo w Polsce to ponad 1 mld zł.
    UtilisationW chwil obecnej jest zainstalowane 5, 3 z tych pięciu pracują, w tym produkt, którego do tej pory nie mieliśmy na rynku, mianowicie Doritosy
  3. Wroclaw.pl (Urząd Miejski Wrocławia)2023
    Original dateLast stated dateInvestor
    Original date · Last stated date31 maja 2023 r. zakład zostanie otwarty.
    InvestorBudimex na zlecenie PepsiCo wybuduje zakład Frito Lay wraz z instalacjami wewnętrznymi, w tym z robotami elektromechanicznymi oraz zagospodarowaniem terenu i infrastrukturą techniczną.
    LocationZakład wybudowany zostanie kilkanaście kilometrów od Wrocławia, na terenie wsi Święte w gminie Środa Śląska
  4. Investmap.plAug 2021
    Construction start
    Construction startUroczyste wmurowanie kamienia węgielnego nastąpiło w dniu 26 sierpnia 2021 r.
  5. Budimex S.A. (generalny wykonawca)May 2023
  6. InvestorFunding
    InvestorThe American company PepsiCo has announced that its fifth – and so far, the largest – investment project in Poland will consist in erecting a new snack factory with an area of approximately seven football fields on a 30-hectare plot in Święte, located near Środa Śląska in Poland’s Dolnośląskie Voivodeship.
    FundingThe US company PepsiCo – one of the world’s largest snack and drink producers – has chosen Święte near Środa Śląska as the location of its new state-of-the-art environmentally friendly production facility. Valued at more than PLN 1 billion, the facility will be the fifth and also the largest PepsiCo investment project in Poland.