EFRA Project (Effective Refining) – Delayed Coking Complex, Grupa LOTOS Refinery in Gdańsk
The EFRA Project (Effective Refining) is a strategic investment by Grupa LOTOS S.A. and its subsidiary LOTOS Asfalt Sp. z o.o., carried out in 2015–2019 at the refinery in Gdańsk (Pomorskie voivodeship). The cost of the project, implemented in 2015–2019, was approximately PLN 2.3 billion. The foundation stone for the construction was laid in October 2015, and construction work on the main installations began in 2016. The heart of the investment is the Delayed Coker Unit (DCU), together with accompanying installations, including a hydrogen generation unit (HGU) and coker naphtha hydrodesulphurisation. The coking complex reached the Ready for Start-Up phase in the first half of 2019, with full load planned for the fourth quarter of 2019; formal completion of the project was confirmed in 2019. Thanks to EFRA, the refinery solved the problem of effectively utilising the heavy residue from crude oil processing, increasing the conversion depth and producing additional fuels and coke from it. The investment enables the production of an additional approximately 900,000 tonnes per year of high-margin fuels (mainly diesel and jet fuel) and approximately 300,000 tonnes of coke.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
Slip: about 2 years vs. the original date (given as a year)
- Construction startOct 2015
- Original dateMar 2018
- Delivery2019
Change history
- 2019stage: operational
- Oct 2015stage: construction
Significance
The EFRA Project was one of Grupa LOTOS's largest industrial investments and significantly increased the crude oil conversion depth at the Gdańsk refinery. The delayed coking unit made it possible to utilise the heavy vacuum residue, converting it into an additional approximately 900,000 tonnes per year of high-margin fuels (mainly diesel and jet fuel) and approximately 300,000 tonnes of coke. The investment raised the group's refining margin and formed part of the refinery's technological modernisation process, which had begun with the earlier Programme 10+.
Sources 6 · 5 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Money.pl / PAP1 Jul 2019CostInvestorSchedule
CostKoszt projektu EFRA realizowanego w latach 2015-2019 to ok. 2,3 mld zł.
InvestorKonsekwencją RFSU jest przekazanie instalacji do rozruchu, czyli do prób i testów jej użytkownikowi - zakładowi EFRA należącym do spółki Lotos Asfalt, właściciela instalacji, podano.
Schedule31 maja Grupa Lotos informowała o przesunięciu terminu osiągnięcia stanu gotowości do rozruchu ostatniego z kompleksów Projektu EFRA - kompleksu koksowania do 30 czerwca 2019.
- Offshore TechnologyConstruction startOriginal date
Construction startThe cornerstone for the construction of the deep oil conversion complex as part of the EFRA project was laid in October 2015. The first stage of construction involved carrying out earthworks to ensure the area and sites were ready for the foundations and piling works of the planned units.
Original dateExpected Completion March 2018
- Oil & Gas JournalApr 2020Stage
Stageboost the Gdańsk refinery's overall production of high-margin products (primarily diesel oil and aviation fuel) by about 900,000 tpy and coke by 300,000 tpy
- NS EnergyStatusDelivery
Status · DeliveryThe EFRA project, which was completed in 2019, involved the installation of a 350,000 tonnes per annum (tpa) DCU
- Funding
Fundingkonsorcjum finansujące udzieliło spółce Lotos Asfalt kredytu inwestycyjnego w wysokości 432 mln dolarów na sfinansowanie 70% wartości inwestycji oraz kredytu obrotowego w kwocie 300 mln zł.
FundingPozostała część nakładów na Projekt EFRA jest finansowana środkami własnymi Grupy Lotos i Lotos Asfalt, w tym pochodzi z emisji akcji Grupy Lotos.
- Funding
FundingJak poinformował resort skarbu, pieniądze pozyskane dzięki objęciu akcji nowej emisji przez Skarb Państwa mają trafić na budowę instalacji opóźnionego koksowania oraz instalacji towarzyszących.