The Eastern Poland Broadband Network (SSPW) was the flagship telecommunications project of the Development of Eastern Poland Operational Programme 2007–2013, implemented in five voivodeships of the macroregion: Podkarpackie, Podlaskie, Lubelskie, Świętokrzyskie and Warmińsko-Mazurskie. Its aim was to counter digital exclusion by building regional backbone and distribution networks in areas at risk of lacking access to fast internet, so that by the end of 2015 broadband services would reach approximately 90% of residents and 100% of public institutions and businesses. According to the project's website, the investment was valued at EUR 300 million and was co-financed at 85% from the European Regional Development Fund. The five regional projects together produced more than 10,000 km of fibre-optic network and around 1,000 nodes. The value of the individual regional components (gross outlays in złoty) included: Lubelskie PLN 385.08 million (2,908 km of network), Warmińsko-Mazurskie almost PLN 330 million (2,292 km, 226 distribution nodes and 10 backbone nodes), Podkarpackie approximately PLN 321 million, Podlaskie approximately PLN 253 million (1,852 km, 181 nodes) and Świętokrzyskie PLN 193.19 million. Implementation spanned 2008–2015 (in Warmińsko-Mazurskie from 1 April 2008 to 31 October 2015). The infrastructure built remains the property of the Eastern Poland voivodeships, and the network is operated commercially by infrastructure operators under a public-private partnership model (in Podlaskie voivodeship, the operator is the Podlaskie Voivodeship itself).
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 carry no assessment yet. How to read this section
Timeline
- Construction start2008
- Delivery2015
Significance
SSPW was the largest telecommunications project in Poland and one of the largest in Europe co-financed from EU funds, covering the entire Eastern Poland macroregion. The backbone and distribution infrastructure built (more than 10,000 km of fibre-optic cable across five voivodeships) was intended to reduce digital exclusion in areas where it was not commercially viable for operators to build networks on their own, and to make it available wholesale to retail operators under an open-access model. The network remains the property of the voivodeship self-governments.
Sources 6 · 5 independent · 3 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Sieć Szerokopasmowa Polski Wschodniej – województwo podlaskieCostInvestorDeliveryStage
CostSieć szerokopasmowa Polski Wschodniej to inwestycja o wartości 300 mln euro
InvestorInfrastruktura wybudowana w ramach projektu jest własnością województw Polski Wschodniej
DeliveryInfrastruktura wybudowana w ramach projektu jest własnością województw Polski Wschodniej, a powstałe sieci są otwarte dla wszystkich zainteresowanych przedsiębiorców telekomunikacyjnych chcących dostarczać usługi szerokopasmowe bezpośrednio odbiorcom końcowym, tj. mieszkańcom, firmom czy instytucjom.
Page of the Podlaskie voivodeship; the network spans the five voivodeships of Eastern Poland.
StageInfrastruktura wybudowana w ramach projektu jest własnością województw Polski Wschodniej, a powstałe sieci są otwarte dla wszystkich zainteresowanych przedsiębiorców telekomunikacyjnych
Page of the Podlaskie voivodeship; the network spans the five voivodeships of Eastern Poland.
- Urząd Marszałkowski Województwa Warmińsko-MazurskiegoConstruction startDeliveryFunding
Construction startOkres realizacji projektu: 01.04.2008 – 31.10.2015
DeliveryOkres realizacji projektu: 01.04.2008 – 31.10.2015.
FundingWojewództwo warmińsko-mazurskie otrzyma na ten cel ze środków EFRR oraz budżetu państwa dofinansowanie w łącznej kwocie 252 970 811,13 zł
FundingWkład Województwa wraz z kwotą podatku VAT wyniesie 74 070 230,94 zł
- PortalSamorzadowy.pl
- [4]Projekt Sieć Szerokopasmowa Polski Wschodniej – województwo podkarpackie – zrealizowany ↗archived ✓Województwo PodkarpackieStatus
StatusWe wszystkich pięciu województwach na terenach zagrożonych wykluczeniem cyfrowym oraz dotkniętych zakłóceniami w funkcjonowaniu rynku, wybudowano regionalne sieci szkieletowe
- PortalSamorzadowy.pl15 Sep 2015Status
StatusZakończono prace związane z budową sieci szerokopasmowej w województwie warmińsko-mazurskim.
The sentence covers one of the five voivodeships (Warmia-Masuria); the other quote covers all five.
- Funding
Funding255 mln euro pochodzić będzie ze środków Europejskiego Funduszu Rozwoju Regionalnego