e-Taxes / e-Declarations (Ministry of Finance IT projects programme, POIG Priority Axis 7, 2007–2015)

completedstage: operational
PLN 900 million
programme budget (multi-year) · data from 2016net or gross: not recorded≈ PLN 900 million (value-by-stage, est., nominal)funding: EU funds, state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A programme of IT projects run by the Ministry of Finance and implemented in 2007–2015 under Priority Axis 7 of the Innovative Economy Operational Programme (Information society, building electronic administration), co-financed at 85% from the European Regional Development Fund. The programme comprised seven IT projects of the finance ministry, including e-Deklaracje (e-Declarations), the e-Podatki (e-Taxes) programme (with e-Deklaracje 2 and e-Rejestracja), the e-Cło (e-Customs) programme (the PUESC Tax and Customs Electronic Services Platform), the Finance Ministry E-Services Infrastructure (IeU), the Consolidation and Centralisation of Customs and Tax Systems (KiC), and the e-Budżet (e-Budget) Platform (modernisation of the TREZOR system). The flagship element was the e-Deklaracje system, launched on 1 January 2008, enabling tax declarations to be filed electronically. According to a statement by Digitisation Minister Anna Streżyńska to the Sejm in May 2016, the total value of the seven IT projects carried out by the Ministry of Finance in 2007–2015 was almost PLN 900 million. The final evaluation report on POIG Priority Axis 7 (2016) found that the axis's projects had strategic significance for improving public services, and that the Ministry of Finance's tax-related projects, which enabled mass electronic filing of declarations, were among the most effective. The stated figure of approximately PLN 900 million covers all seven systems of the ministry (taxes, customs, budget, infrastructure), not e-Deklaracje alone.

How it went

Assessment: settled, as of 2016. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Utilisationin use[6]
masowe elektroniczne składanie deklaracji podatkowych przez system e-Deklaracje
Current
system e-Deklaracje w powszechnym użyciu; ok. 23% przedsiębiorców korzystało z e-Deklaracji (badanie w raporcie ewaluacyjnym 7. osi POIG, 2016)

Timeline

  1. Delivery2015

Significance

The programme launched mass electronic tax services for the state: the e-Deklaracje system (from 1 January 2008) enabled tax returns and declarations to be filed online, while subsequent projects (e-Podatki, e-Rejestracja, the tax portal, e-Cło/PUESC) built the backbone of the digital tax administration. The final evaluation report on POIG Priority Axis 7 rated the Ministry of Finance's tax-related projects among the most effective and most widely used, enabling mass use of electronic declaration filing. At the same time, political criticism (a 2016 Sejm statement) noted that despite spending of almost PLN 900 million on the ministry's seven projects, some services for citizens remained unfinished.

Sources 6 · 5 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Cyfryzacji (gov.pl)12 May 2016
    CostFunding
    Costłączna wartość siedmiu projektów IT, które realizowało Ministerstwo Finansów w latach 2007-2015 wynosi prawie 900 milionów złotych
    Fundingdofinansowania unijnego w wysokości 85% wartości Programu (a więc ok. 3,4 mld złotych ze środków unijnych)
    Fundingwkładem własnym w wysokości 600 milionów złotych (wkład krajowy)
  2. Forsal.pl11 May 2016
  3. Ministerstwo Rozwoju / ewaluacja.gov.pl2016
    StatusDeliveryInvestor
    Status · DeliveryDo 31 grudnia 2015 r. zakończono realizację 36 projektów (w tym projekt systemowy) na łączną wartość dofinansowania 2 630 mln zł.
    InvestorNazwa projektu: e-Deklaracje 2 Beneficjent: Ministerstwo Finansów
  4. Wikipedia (pl)
    Stage
    StageSystem e-Deklaracje został uruchomiony 1 stycznia 2008 r.
  5. Ministerstwo Finansów / KAS (gov.pl)
  6. Utilisation
    UtilisationOd sierpnia 2015 dzięki systemowi podatnicy zarejestrowali blisko pół miliona pism w izbach skarbowych i urzędach skarbowych, a w tym miesiącu e-Podatki przyjmują nawet do 65 000 deklaracji tygodniowo