Electronic Platform for Collecting, Analysing and Sharing Digital Resources on Medical Events (P1, e-Health)
Project P1, the Electronic Platform for Collecting, Analysing and Sharing Digital Resources on Medical Events, is the central system for digitising healthcare in Poland, built in stages since 2007. Phase 1 (2007–2015) covered the design and development of the platform's products (subsystems); its total implementation cost was set at PLN 712,640,000.00, of which approximately 85% was to come from EU funds under the Innovative Economy Operational Programme. The project was managed by the Centre for Health Information Systems (CSIOZ), transformed in 2020 into the e-Health Centre. Phase 1 failed to meet its planned deadlines. In February 2016 it was reported that the P1 Platform was not functioning as a whole, and identified irregularities and reports to the prosecutor's office led to the termination of contracts with contractors and a 'fresh start' for the project. Key e-services were rolled out in subsequent years: the e-prescription became mandatory nationwide from 8 January 2020, followed by the launch of e-referral, the Patient's Internet Account (together with the mojeIKP application), medical events, and the exchange of electronic medical records. Phase 2 (2016–2022) and the currently ongoing Phase 3 continue the platform's development.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section
- Current
- ogólnopolska platforma P1 działa
Timeline
- Announced2007
- Construction start2007
Significance
The P1 Platform is the largest healthcare digitisation project in Poland, creating a central, nationwide infrastructure for exchanging medical data. It underpins widely used health e-services, including the e-prescription, e-referral and the Patient's Internet Account, used by patients and medical facilities across the country. After a difficult start burdened by the delays and irregularities of Phase 1, the system became the foundation of Poland's healthcare digitisation and allows facilities to exchange medical records electronically free of charge.
Sources 6 · 6 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Centrum e-ZdrowiaAnnouncedConstruction startUtilisation
AnnouncedFaza 1 w latach 2007-2015
Construction startProjekt jest realizowany od 2007 roku
UtilisationSystem e-zdrowie (P1) tworzą cyfrowe usługi (e-recepta, e-skierowanie, EDM, ZM), aplikacje (Internetowe Konto Pacjenta, mojeIKP, gabinet.gov.pl) oraz rozwiązania usprawniające procesy planowania i realizacji świadczeń ochrony zdrowia.
- Gazeta Prawna18 Feb 2016Funding
FundingProjekt był wyceniony na 712 mln zł, a 85 proc. tej kwoty miało pochodzić z funduszy unijnych.
- testerzy.plCostInvestorFundingScheduleBudget
CostCałkowity koszt realizacji projektu wynosi 712 640 000,00 zł.
InvestorKomunikat CSIOZ, który zarządza projektem
Funding · ScheduleJednak ze względu na opóźnienia w realizacji tego przedsięwzięcia, zwanego też systemem e-Zdrowie, jego koszty w znacznej mierze zostaną pokryte ze środków krajowych.
BudgetCałkowity koszt realizacji projektu wynosi 712 640 000,00 zł. [ten koszt już został przekroczony - przypomnienie redakcji]
- [4]E-recepta obowiązkowa od 8 stycznia 2020 r., a na miesiąc przed tylko 55 proc. placówek podłączona do P1 ↗archived ✓Prawo.pl11 Dec 2019
- Najwyższa Izba Kontroli21 Mar 2023StatusStageUtilisation
Status · Stage · Utilisationjuż działająca ogólnopolska platforma P1 umożliwia placówkom zdrowotnym w całym kraju bezpłatną wymianę dokumentów
- Rzeczpospolita20 Mar 2018