Diesel Hydrodesulphurisation Unit HON VII (PKN Orlen, Płock)

completedstage: operationaldelivered
PLN 500 million
programme budget (multi-year) · data from Nov 2010net or gross: not recorded≈ PLN 500 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Diesel Hydrodesulphurisation Unit HON VII is a desulphurisation unit at the PKN Orlen production plant in Płock, commissioned on 2 November 2010 after a construction process of about two years. The investment cost around PLN 500 million. The unit has a throughput capacity of 260 tonnes per hour, or 2.2 million tonnes of fuel a year, and it increased the Płock refinery's diesel production capacity by around 1 million tonnes a year. The unit comprises a desulphurisation section and an amine section for removing hydrogen sulphide and ammonia; after it was commissioned, the older HON II and HON III units were taken out of service. The investment's contractors included Technip Italy and Technip Polska, Albemarle Catalyst, Orlen Projekt, Mostostal Płock and Pol-Aqua.

How it went

Assessment: settled, as of 2 Nov 2010. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[3]

Timeline

  1. Delivery2 Nov 2010

Significance

The commissioning of the HON VII unit increased the PKN Orlen Płock refinery's production capacity for high-quality diesel by around 1 million tonnes a year, helping to meet domestic fuel demand and to produce diesel meeting tightened quality standards. The unit, with a throughput capacity of 260 tonnes per hour, replaced the worn-out, older desulphurisation units (HON II and HON III).

Sources 4 · 4 independent · 2 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. PKN Orlen S.A.2 Nov 2010
    Cost
    CostProces budowy nowej instalacji HON VII, której koszt wyniósł ok. 500 mln PLN, trwał dwa lata.
  2. WNP.plNov 2010
    Stage
    StageZdolność przerobowa instalacji HON VII wynosi 260 ton na godzinę, czyli 2,2 mln ton paliw rocznie
  3. Bankier.plNov 2010
    StatusDeliveryInvestor
    Status · Delivery · InvestorPKN Orlen oddał we wtorek do użytku w zakładzie produkcyjnym w Płocku nową instalację