DCT Gdańsk deepwater container terminal (Baltic Hub) – Terminal T2

completedstage: operationaldelivered
EUR 200 million
estimate · data from 2014net or gross: not recorded≈ PLN 860 million (value-by-stage, est., nominal)funding: private finance, multilateral development bank, the investor’s own fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The second deepwater quay (T2) of the DCT Gdańsk container terminal (Baltic Hub since 2022) in the Northern Port of Gdańsk, located between the existing T1 quay and the ore pier. DCT Gdańsk began construction at the start of 2015, and the new quay, about 650 m long (about 656 m according to the contractor) with a depth alongside of up to 17 m, was officially opened on 24 October 2016. The quay was equipped with 5 ship-to-shore (STS) gantry cranes, which allowed DCT Gdańsk's handling capacity to double from about 1.5 million to about 3 million TEU a year. The general contractor and designer was the Belgian company N.V. BESIX, with the Polish company NDI as its main subcontractor. The total cost of building the terminal was estimated at about EUR 200 million (some sources give about EUR 250 million); the operator remained DCT Gdańsk S.A.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[2]
Scheduleon time[2]
Budgeton budget[2]

Timeline

  1. Construction start2015
  2. Delivery24 Oct 2016

Change history

  • 24 Oct 2016stage: operational
  • 2015stage: construction

Significance

The opening of the second deepwater quay, T2, in October 2016 doubled DCT Gdańsk's handling capacity from about 1.5 million to about 3 million TEU a year, strengthening the terminal's position as the largest and most modern maritime container terminal in Poland and a key container hub on the Baltic. The new quay, about 650 m long with a depth of up to 17 m and equipped with 5 STS cranes, made it possible to handle simultaneously the largest transoceanic container ships calling directly at the Baltic Sea.

Sources 7 · 5 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Money.pl8 Dec 2014
    CostFunding
    CostCałkowity koszt budowy terminalu to ok. 200 mln euro
    Funding290 mln euro kredytu na budowę drugiego głębokowodnego nabrzeża w DCT Gdańsk udzieli grupa banków komercyjnych i wspierających rozwój.
  2. PortalMorski.pl24 Oct 2016
    StatusStageDeliveryBudgetSchedule
    Status · DeliveryW południe, 24 października, oficjalnie otwarto drugie głębokowodne nabrzeże terminalu kontenerowego DCT Gdańsk.
    Stageprzyczyni się do podwojenia potencjału przeładunkowego DCT Gdańsk do 3 milionów TEU rocznie.
    DeliveryW dniu 24 października 2016 r. nastąpiło oficjalne otwarcie drugiego głębokowodnego nabrzeża kontenerowego DCT Gdańsk.
    Budget · ScheduleBudowa nabrzeża T2 została zakończona zgodnie z harmonogramem i w ramach planowanego budżetu.
  3. Trojmiasto.pl24 Oct 2016
    Construction startInvestor
    Construction start · InvestorDCT Gdańsk rozpoczął budowę drugiego głębokowodnego nabrzeża w Porcie Północnym na początku 2015 roku.
  4. Wikipedia (pl)
  5. NDI S.A.
  6. Funding
    FundingThe EBRD loan will be in an amount of up to €75 million representing up to 25% of the total project costs.
    FundingThe remaining funding for the project is expected to be provided by other financial institutions as well as cash flows generated by the existing terminal facility.