A data center planned on the 53-hectare site of the former Fiat engine plant in Bielsko-Biała by the Katowice-based developer DL Invest Group, together with the cloud gaming provider Boosteroid. The investment is reported at about one billion dollars. The first phase is to offer more than 50 MW of IT capacity, expandable to 200 MW. The site has its own 82 MW power supply. The project was announced in February 2026. The sources give no schedule or permits yet.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- AnnouncedFeb 2026
Significance
The project reuses existing industrial infrastructure, including the 82 MW power point, and is to be the first of up to 12 data centers in the joint venture of DL Invest and Boosteroid in Europe. The investor also announces an R&D facility and new jobs.
Sources 4 · 4 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Telecompaper5 Mar 2026StatusStage
Status · StagePolish property developer DL Invest Group announced the development of a data centre in the city of Bielsko-Biala in southern Poland, representing an investment of approximately USD 1 billion.
- GazetaPrawna.pl14 Feb 2026CostAnnounced
CostPlanowana inwestycja w Bielsku-Białej ma wartość około miliarda dolarów.
AnnouncedNa terenie dawnej fabryki silników Fiata w Bielsku-Białej powstanie jedno z największych centrów danych w Polsce.
- [3]Koniec produkcji samochodów, czas na serwery. W Bielsku-Białej powstanie potężne centrum danych ↗PropertyNews.pl24 Feb 2026
- ITwiz27 Mar 2026Investor
InvestorProjekt realizowany przez DL Invest Group we współpracy z Boosteroid