ArcelorMittal: blast furnace no. 2 overhaul (Dąbrowa)

completedstage: operational
PLN 720 million
estimate · data from 10 Aug 2023net or gross: not recorded≈ PLN 720 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A major overhaul of blast furnace no. 2 at the Dąbrowa Górnicza plant of ArcelorMittal Poland, begun at the end of March 2023. The scope covered replacing the carbon lining in the hearth, a new cooling system and a blast furnace gas cleaning plant. The company puts the investment at over PLN 720 million. The overhaul was completed, as the company announced on 10 August 2023. The amount comes from company statements and is not backed by a contract or a public document.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction startMar 2023
  2. DeliveryAug 2023

Significance

According to the company, the upgrade will cut CO2 emissions by almost 45,000 tonnes a year. Money.pl quotes the chief executive calling it the company's largest investment project since the hot rolling mill in Kraków was built in 2007.

Sources 3 · 3 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. ArcelorMittal Poland10 Aug 2023
    StatusStageCostConstruction startDeliveryInvestor
    Status · Stage · DeliveryZakończył się remont wielkiego pieca numer 2, w dąbrowskim oddziale ArcelorMittal Poland.
    Cost · Construction startWarta ponad 720 mln zł inwestycja, która rozpoczęła się pod koniec marca
    Investorw dąbrowskim oddziale ArcelorMittal Poland
  2. Kurier Kolejowy10 Aug 2023
  3. money.pl24 Mar 2023