New ArcelorMittal Poland Hot Rolling Mill in Kraków (former Sendzimir Steelworks)
The new hot rolling mill at the group's Kraków branch (in 2007, Mittal Steel Poland; the former Tadeusz Sendzimir Steelworks in the Nowa Huta district) was the largest processing investment at the Kraków plant. Construction began in 2005, and in 2007 the first slab was heated in the new furnace; the installation was commissioned in 2007 at a cost of approximately PLN 1.2 billion. The mill produces hot-rolled sheet steel for, among others, the automotive and household-appliance industries; the hot rolling mill facility itself absorbed approximately PLN 1.2 billion, and the group has invested more than PLN 3 billion in the former Sendzimir Steelworks since its privatisation in 2004. Following the 2016 expansion (a second heating furnace), the rolling line reached a capacity of around 3.3 million tonnes per year and is still regarded as the most modern hot rolling mill in Europe.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- ok. 3,3 mln ton blach rocznie (2016)
- Capacity or target
- 2,3 mln ton rocznie (przy uruchomieniu w 2007)
Timeline
- Construction start2005
- Delivery2007
Change history
- 2007stage: operational
- 2005stage: construction
Significance
The new hot rolling mill was the largest processing investment at the Kraków plant following the privatisation of the former Sendzimir Steelworks, and enabled the group to supply hot-rolled sheet steel to the automotive and household-appliance industries. Together with the 2016 expansion, it remains regarded as the most modern hot rolling mill in Europe, with its rolling line reaching a capacity of around 3.3 million tonnes of sheet steel per year.
Sources 6 · 4 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- ArcelorMittal PolandStatusStageCostDelivery
Status · Stage · Cost · DeliveryWalcownia gorąca blach, uruchomiona w roku 2007 kosztem 1,2 mld zł i rozbudowana w roku 2016 nadal pozostaje najnowocześniejszą walcownią w Europie.
- Zrobotyzowani.com.plConstruction startUtilisation
Construction startBudowa ruszyła w 2005 roku, a już w 2007 roku wygrzano w nowym piecu pierwszy slab
UtilisationAle walcownia gorąca wciąż żyje pełnią życia, przetwarzając stalowe półprodukty (slaby) przywożone z innych zakładów grupy, nie tylko z Polski.
- Wikipedia (pl)Investor
InvestorW maju 2019 właściciel huty, spółka ArcelorMittal Poland, podjął decyzję o wygaszeniu wielkiego pieca i stalowni z powodu wysokich cen energii elektrycznej, praw do emisji dwutlenku węgla i światowego spowolnienia na rynku stali[5].
- WNP.PL – Portal gospodarczy (serwis Hutnictwo / Nowy Przemysł)29 Jun 2007Investor
InvestorNowa walcownia gorąca blach w krakowskim oddziel Mittal Steel Poland, zbudowana za 1.240 mln zł, zostanie oficjalnie oddana do użytku 27 lipca.
- Biznes Interia (Interia.pl)8 Aug 2024StatusStageCostDelivery
Status · Stage · Cost · DeliveryWarto wiedzieć, że nowa walcownia gorąca blach, uruchomiona w roku 2007 kosztem 1,2 mld zł i rozbudowana w roku 2016 nadal pozostaje najnowocześniejszą walcownią w Europie.