Modernisation and construction of air base infrastructure for F-16 aircraft (Poznań-Krzesiny and Łask)
Between 2001 and 2008, the infrastructure of two tactical air bases, the 31st Tactical Air Base at Poznań-Krzesiny (Greater Poland Voivodeship) and the 32nd Tactical Air Base at Łask (Łódź Voivodeship), was modernised and expanded to base 48 F-16C/D Block 52+ multirole aircraft. Investment works at the Poznań-Krzesiny airfield began in 2001, that is, 1.5 years before the multirole aircraft was selected (27 December 2002) and the contract for delivery of the 48 aircraft was signed (18 April 2003). The aircraft were delivered between 2006 and 2008; the first F-16s landed at Krzesiny in November 2006. The scope of works included new runways and taxiways, apron areas, and maintenance and overhaul hangars, among other elements. According to findings by the Supreme Audit Office (NIK), as of 31 December 2010 the aircraft programme's expenditure on the modernisation of the Poznań-Krzesiny and Łask airfields alone was put at PLN 1,813,355 thousand. NIK criticised the process for selecting the base location and the start of some works before the aircraft was formally selected.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Current
- 31 BLT Poznań-Krzesiny eksploatuje dwie eskadry F-16 C/D; obie bazy czynne (2026)
- Capacity or target
- 48 samolotów F-16C/D Block 52+
Timeline
- Construction start2001
- Delivery2008
Significance
The modernised infrastructure at Krzesiny and Łask became the basis for basing Poland's first F-16 aircraft, at the time the most modern combat fleet of the Polish Air Force. The 31st Tactical Air Base at Poznań-Krzesiny was the first base to receive F-16s and operates two squadrons of these aircraft, while the second base (Łask) supplements the multirole aviation capability. The programme required the construction of new runways, taxiways and maintenance hangars meeting F-16 operating standards.
Sources 5 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Altair Agencja Lotnicza7 Nov 2011StatusCostConstruction startDeliveryFundingScheduleBudget
Status27 grudnia 2002 ogłoszony został wybór samolotu F-16 na samolot wielozadaniowy dla Sił Zbrojnych RP, a w dniu 18 kwietnia 2003 podpisano umowę na dostawę 48 samolotów. Zostały one dostarczone w latach 2006-2008.
Costna dzień 31 grudnia 2010, wydatki programu samolotowego tylko na modernizację lotnisk Poznań-Krzesiny i Łask określono na 1.813.355 tys. zł.
Construction startNa terenie lotniska Poznań-Krzesiny od 2001 w ramach programu samolotowego realizowane były zadania inwestycyjne
Deliverykoszt kompleksowej modernizacji 7 podstawowych lotnisk wojskowych (stałego bazowania), w latach 2001-2008, w tym lotniska Poznań-Krzesiny określono na 1.329.367 tys. zł
Fundingpo zatwierdzeniu przez MON w 2010 korekty nr 7 ww. planu, przewidziana w nim wartość powyższych wydatków - na dzień 31 grudnia 2010 - wynosiła 1.813.355 tys. zł
ScheduleOpóźnienia w realizacji inwestycji kontynuowanych, bądź trudności w przekazaniu do eksploatacji niektórych obiektów wykonanych w ramach zadań inwestycyjnych, utrudniają realizację zadań Bazy, powodując także wzrost ich kosztów.
BudgetInformacja... pokazuje, jak bardzo pierwotnie zaniżano koszty inwestycji: Dowództwo WLOP w 2001 oszacowało na 205.855 tys. zł koszt dostosowania w latach 2001-2006 lotniska Poznań-Krzesiny do bazowania samolotów wielozadaniowych.
- Najwyższa Izba Kontroli3 Nov 2011Investor
InvestorW okresie od 1 stycznia 2006 r. do 30 września 2009 r. Wojskowy Zarząd Infrastruktury w Poznaniu, na podstawie wyroków sądowych, wypłacił właścicielom nieruchomości zlokalizowanych na obszarze ograniczonego użytkowania utworzonego wokół lotniska Poznań-Krzesiny odszkodowania, w łącznej kwocie 2.007,6 tys. zł
- Wikipedia (en)StageUtilisation
Stage · UtilisationThe unit operates two squadrons of F-16 C/D fighters (16 planes in each squadron).
- Infolotnicze.pl (autor: dr Krzysztof Kuska)6 Oct 2017Construction start
Construction startW podpoznańskich Krzesinach w 2001 roku rozpoczęło się układanie nowych nawierzchni betonowych i pasa startowego o długości 2500 metrów i szerokości 60 metrów z systemem lin hamujących samoloty.
- Najwyższa Izba Kontroli3 Nov 2011P/09/084/KOB