A4 Motorway Zgorzelec – Krzyżowa

completedstage: operationaldelivered
PLN 1.1 billion
EU-eligible cost · data from 2009net or gross: not recorded≈ PLN 1.1 billion (value-by-stage, est., nominal)funding: EU funds, state special fundLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of a new, approximately 51.4 km section of the A4 motorway from the Polish-German border at Zgorzelec to the Krzyżowa interchange (connecting with the A18 motorway) in Lower Silesian Voivodeship, carried out by the General Directorate for National Roads and Motorways (GDDKiA). The project was divided into two sections: "A" Zgorzelec – Wykroty (km 0+000 to 22+000) and "B" Wykroty – Krzyżowa (km 22+000 to 51+400). Construction contracts for both sections were signed on 9 November 2006, and works were carried out from 2007. The motorway was opened to traffic on 14 August 2009. The project was co-financed from European Union Cohesion Fund resources: the co-financing amounted to PLN 865,461,438.70 against a total project value of PLN 1,137,798,370.84 (the Cohesion Fund grant covered 82% of eligible costs). The section forms the western, border-adjacent part of the A4 motorway corridor linking Poland with Germany's road network.

How it went

Assessment: settled, as of 14 Aug 2009. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[3]

Timeline

  1. Delivery14 Aug 2009

Change history

  • 14 Aug 2009stage: operational
  • 9 Nov 2006stage: construction

Significance

The Zgorzelec – Krzyżowa section closed the western, border-adjacent part of the A4 motorway and connected Poland's motorway network with Germany's road network at the Zgorzelec crossing, creating a continuous east-west transit motorway link through Lower Silesia. It was one of the largest road projects co-financed from the Cohesion Fund in Poland under the 2004–2006 financial perspective, with a value exceeding one billion zloty. The new route took over transit traffic from the region's congested national roads and shortened journey times towards the border.

Sources 4 · 3 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)
    StatusDelivery
    Status · Delivery14.08.2009 r. – oddanie do użytkowania
  2. Ministerstwo Funduszy i Polityki Regionalnej (mapadotacji.gov.pl)
    CostInvestorFunding
    Costwartość projektu 1 137 798 370,84 zł
    Investornazwa beneficjenta Generalna Dyrekcja Dróg Krajowych i Autostrad
    Fundingdofinansowanie z UE 865 461 438,70 zł
  3. Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)
    StageDelivery
    Stage · DeliveryData oddania do ruchu: 14.08.2009 r.
  4. Funding
    FundingW latach 2005–2006 KFD finansował m.in. odcinki A4: Zgorzelec – Krzyżowa, Krzywa – Wrocław, Kleszczów – Sośnica i Sośnica – Murckowska