A4 Motorway Tarnów (Krzyż interchange) – Rzeszów (Rzeszów Wschód interchange), including a section of the S19 expressway (Rzeszów Zachód interchange – Świlcza interchange)

completedstage: operational
PLN 5.3 billion
programme budget (multi-year) · data from 2015net or gross: not recorded≈ PLN 5.3 billion (value-by-stage, est., nominal)funding: EU funds, state special fundLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of the A4 motorway in the Tarnów–Rzeszów corridor, on the section from the Krzyż interchange (east of Tarnów) to the Rzeszów Wschód interchange, together with the associated section of the S19 expressway from the Rzeszów Zachód interchange to the Świlcza interchange. The project of the General Directorate for National Roads and Motorways (GDDKiA) was carried out as a single project co-financed from European Union funds (the Cohesion Fund, under the Operational Programme Infrastructure and Environment 2007–2013); the co-financing agreement was signed on 30 June 2010. Works on the main Dębica Pustynia – Rzeszów Zachód section began on 9 June 2010. The new motorway was built in stages: on 30 October 2013 drivers could use the section from Dębica to Rzeszów, and on 30 October 2014 the Tarnów (Krzyż interchange) – Dębica Pustynia section opened, closing a continuous motorway link from Kraków to Rzeszów. Under the contract annex, the completion date for the whole project was 30 June 2015. The main contractors included Budimex S.A. (Dębica Pustynia – Rzeszów Zachód section), STRABAG (Krzyż – Dębica Pustynia section), Mostostal Warszawa S.A., Eurovia Polska S.A. and Heilit + Woerner Sp. z o.o. The total project value was PLN 5,295,490,059.90, of which the maximum EU co-financing amount was PLN 2,969,050,618.42.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction start9 Jun 2010
  2. Last stated date30 Jun 2015
  3. Delivery30 Oct 2014

Change history

  • 30 Oct 2014stage: operational
  • 30 Oct 2013stage: operational
  • 9 Jun 2010stage: construction

Significance

The A4 Tarnów (Krzyż interchange) – Rzeszów section closed a continuous motorway link from the Kraków metropolitan area to Rzeszów, cutting the Kraków–Rzeszów journey time by roughly half an hour. The motorway is part of the Trans-European Transport Network (TEN-T) east-west corridor, providing a connection to Germany (via the border crossing at Jędrzychowice) and to Ukraine (via the border crossing at Korczowa). The associated S19 Rzeszów Zachód – Świlcza section linked the new motorway into the region's expressway network.

Sources 8 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA (serwis archiwalny)
    CostLast stated dateFunding
    CostCałkowita wartość projektu: 5 295 490 059,90 PLN
    Last stated dateData zakończenia realizacji projektu wg Aneksu: 30.06.2015 r.
    FundingMaksymalna kwota dofinansowania z UE: 2 969 050 618,42 PLN
  2. Mapa Dotacji UE (gov.pl)
    Investor
    Investornazwa beneficjenta Generalna Dyrekcja Dróg Krajowych i Autostrad
  3. GDDKiA (serwis archiwalny)30 Oct 2014
    StageDeliveryStatus
    Stage35 km odcinek A4 Tarnów - Dębica został udostępniony kierowcom przed Dniem Wszystkich Świętych.

    The sentence covers the route's last section to open (Tarnów – Dębica, 30 October 2014); the Dębica Wschód – Rzeszów Północ section opened on 30 October 2013.

    Delivery · StatusOtwarto odcinek z Tarnowa do Dębicy 30-10-2014 35 km odcinek A4 Tarnów - Dębica został udostępniony kierowcom przed Dniem Wszystkich Świętych.

    Release on the route's last section to open (Tarnów – Dębica, 30 October 2014); the Dębica Wschód – Rzeszów Północ section opened on 30 October 2013.

  4. GDDKiA (serwis archiwalny)30 Oct 2013
    Stage
    StageOd 30 października 2013 r. kierowcy mogą już korzystać z nowego, 37-kilometrowego odcinka autostrady A4

    The sentence covers the Dębica Wschód – Rzeszów Północ section (37 km, 30 October 2013); the route's last section, Tarnów – Dębica, opened on 30 October 2014.

  5. STRABAG Sp. z o.o.
  6. GDDKiA (serwis archiwalny)
    Construction start
    Construction start09.06.2010 - data rozpoczęcia robót
  7. Funding
    FundingOddział przedłożył do BGK wnioski o wypłatę środków z Krajowego Funduszu Drogowego w terminie umożliwiającym ich terminową realizację.