The first newly built section of the A4 motorway east of Kraków, 19.9 km long, between the Wielicka interchange and the Szarów interchange, forming part of the A4 Kraków – Tarnów route on the European east-west corridor leading towards the border with Ukraine. The investor was the General Directorate for National Roads and Motorways, and the contractor was a Spanish-Polish consortium made up of DRAGADOS SA and Polimex - Mostostal SA. The construction contract was worth PLN 839,328,570.79 gross. Construction started on 27 April 2007 and finished on 30 September 2009; the section's official opening took place on 29 October 2009, and drivers were able to use it from as early as 28 October 2009. The total cost of the task, including land purchase and other expenses, exceeded one billion zloty. The section is a free, dual-carriageway motorway managed by GDDKiA.
How it went
Assessment: settled, as of 29 Oct 2009. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- odcinek otwarty do ruchu 28–29 października 2009 r. i eksploatowany jako bezpłatna autostrada A4
Timeline
- Construction start27 Apr 2007
- Delivery30 Sep 2009
Change history
- 29 Oct 2009stage: operational
- 27 Apr 2007stage: construction
Significance
The Kraków – Szarów section was the first newly built fragment of the A4 motorway running east of Kraków and opened up construction of the A4 Kraków – Tarnów route, key to the European east-west road corridor (A4) towards the border crossing with Ukraine. It included 30 engineering structures (viaducts, flyovers, a wildlife crossing), and the road became a free element of the national motorway network managed by GDDKiA.
Sources 3 · 3 independent · 2 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- GDDKiA2009StatusStageCostConstruction startDeliveryInvestorFundingUtilisation
Status · Stage · UtilisationKierowcy mogli pojechać nią już 28 października, z czego wielu skwapliwie skorzystało.
CostKontrakt opiewał na kwotę 839.328.570,79 złotych brutto.
Construction start · DeliveryBudowa autostrady A4 Kraków – Tarnów odcinek Kraków – Szarów ruszyła 27 kwietnia 2007 roku, a zakończyła się 30 września 2009 roku.
InvestorInwestorem zadania była Generalna Dyrekcja Dróg Krajowych i Autostrad
FundingBudowa została sfinansowana w całości z Krajowego Funduszu Drogowego.
- Money.pl2007
- Auto Świat29 Oct 2009StatusDelivery
Status · DeliveryWojewódzki Inspektor Nadzoru Budowlanego w Krakowie wydał warunkowe pozwolenie na użytkowanie nowo powstałego 20-kilometrowego odcinka autostrady z Krakowa do Szarowa.