A4 Motorway Jarosław – Korczowa (Ukrainian border)

completedstage: operationaldelivered
PLN 1.8 billion
contract value · data from 2009net or gross: not recorded≈ PLN 1.8 billion (value-by-stage, est., nominal)funding: EU fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The final, approximately 47-kilometre section of the A4 motorway from Jarosław to Korczowa at the Polish-Ukrainian border, closing the Polish part of the A4/E40 corridor (Berlin-Kyiv). The investment was divided into two work packages carried out under the "design and build" system: Jarosław (Wierzbna interchange) - Radymno, approximately 25 km long, built by the Budimex Dromex and Ferrovial Agroman consortium for PLN 969.2 million, and Radymno - Korczowa (state border), approximately 22 km long, built by the Greek company J&P Avax for PLN 818.5 million. Bids in the GDDKiA tender were opened on 7 September 2009. The GDDKiA investor's cost estimate assumed an investment cost from Jarosław to Korczowa of PLN 2.35 billion, and the selected bids allowed savings of around PLN 560 million to be forecast against the estimate; the whole investment was valued at approximately PLN 1.7-1.8 billion. The original completion deadline was April 2012. The main carriageway of the Radymno-Korczowa section was made available to drivers on 23 December 2013, and the Korczowa interchange, the last interchange in Poland and the European Union before crossing the Polish-Ukrainian border, was opened to traffic on 18 June 2014. The investor was the General Directorate for National Roads and Motorways (GDDKiA).

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 have an assessment with no confirmed quote. How to read this section

Deliverydelivered[4]

Timeline

  1. Announced2009
  2. Original dateApr 2012
  3. Delivery2013

Change history

  • 23 Dec 2013stage: operational

Significance

The Jarosław – Korczowa section closed the Polish part of the A4 motorway all the way to the border with Ukraine, creating a continuous motorway connection on the European east-west corridor (A4/E40, towards Berlin-Kyiv). The Korczowa interchange is the last road junction in Poland and the European Union allowing drivers to exit the A4 motorway before crossing the Polish-Ukrainian border, which makes the section a key element of the road border crossing and of freight transit to the east. The investment was completed for less than the GDDKiA investor's cost estimate (PLN 2.35 billion), with forecast savings of around PLN 560 million.

Sources 6 · 3 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Auto Świat2009
    AnnouncedInvestor
    Announced · Investor7 września 2009 roku w oddziale Generalnej Dyrekcji Dróg Krajowych i Autostrad w Rzeszowie zostały otwarte oferty
  2. GDDKiA2009
    Original date
    Original dateTermin realizacji to kwiecień 2012 r.
  3. muratorplus.pl
    Cost
    CostKonsorcjum firm, w składzie: Budimex Dromex i Ferrvial Agroman z Hiszpanii, za 969,2 mln zł wybuduje 25-kilometrowy, podkarpacki fragment autostrady A4 na odcinku Jarosław (węzeł Wierzbna) - Radymno. Zaś 22-kilometrowy odcinek Radymno-Korczowa (granica państwa) wybuduje grecka firma J&P Avax, za 818,5 mln zł. Całość inwestycji będzie kosztować 1,7 mld zł
  4. GDDKiA2014
    StatusStageDelivery
    Status · DeliveryCiąg główny tego odcinka A4 został udostępniony kierowcom 23 grudnia 2013 r.
    StageOd dziś kierowcy podróżujący autostradą A4 mogą korzystać z węzła Korczowa.
  5. GDDKiA
  6. Funding
    Fundingwartość dofinansowania projektu z Programu Infrastruktura i Środowisko wynosi 1,020 mld złotych