A1 motorway Pyrzowice – Piekary Śląskie

completedstage: operationaldelivered
PLN 1.5 billion
contract value · data from 2009net or gross: not recorded≈ PLN 1.5 billion (value-by-stage, est., nominal)funding: EU fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of the northernmost, 16.07-kilometre section of the A1 motorway in the Silesian Voivodeship, from the Pyrzowice interchange (near Katowice-Pyrzowice Airport) to the Piekary Śląskie interchange, along km 442+500 to 459+200. The investor was the General Directorate for National Roads and Motorways (GDDKiA), Katowice branch, and the contractor was a consortium of BUDIMEX S.A. (leader) and Mostostal Warszawa (partner). The construction contract was signed on 27 July 2009, works began on 20 August 2009, and the section was opened to traffic on 1 June 2012. The value of the construction contract for the section was approximately PLN 1.5 billion net (nearly PLN 1.83 billion with 22 percent VAT). The investment produced a motorway with two dual carriageways separated by a median strip, two interchanges (Pyrzowice and Piekary), 19 bridge structures, access roads, and two rest areas.

How it went

Assessment: settled, as of 1 Jun 2012. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Scheduleahead of schedule[4]

Timeline

  1. Construction start20 Aug 2009
  2. Delivery1 Jun 2012

Change history

  • 1 Jun 2012status: completedOddanie odcinka Pyrzowice – Piekary Śląskie do ruchu.
  • 1 Jun 2012stage: operational

Significance

The Pyrzowice – Piekary Śląskie section formed the northern part of the Silesian stretch of the A1 motorway (Pyrzowice – Maciejów – Sośnica), closing the motorway connection between the Upper Silesian agglomeration and Katowice-Pyrzowice Airport and further to the north. The route is part of the north-south corridor connecting the Tricity with the Czech border. The section was built as a motorway with a 2+2 cross-section with reserve capacity, together with the Pyrzowice and Piekary interchanges and 19 bridge structures.

Sources 6 · 4 independent · 2 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)
    StatusStageConstruction startDelivery
    Status · Stage · DeliveryOddanie do ruchu 1 czerwca 2012 roku
    Construction startRozpoczęcie robót: 20.08.2009 r.
  2. Money.pl9 May 2012
    Cost
    Costwartą 1,5 mld zł umowę na budowę A1 między Piekarami a Pyrzowicami
  3. Auto ŚwiatJul 2009
  4. Money.pl / PAP28 May 2012
    InvestorSchedule
    InvestorWedług informacji katowickiego oddziału Generalnej Dyrekcji Dróg Krajowych i Autostrad odcinek ten ma być otwarty dla kierowców na przełomie maja i czerwca.
    SchedulePrace między Pyrzowicami, a Piekarami Śląskimi zakończyły się 9 maja - kilka tygodni przed umownym terminem 16 czerwca.
  5. Funding
    FundingCo-financing from the EU 4 652 614 238,23 zł
    Fundingprogram Program Operacyjny Infrastruktura i Środowisko action VI.1. Rozwój sieci drogowej TEN-T fund Fundusz Spójności perspective 2007 - 2013