190 MWe Combined-Cycle Gas Turbine Block at the 'Zielona Góra' CHP Plant
A combined-cycle gas turbine block with an electrical output of 190 MWe and a thermal output of 95 MWt, built at the 'Zielona Góra' CHP plant (Elektrociepłownia 'Zielona Góra' S.A.) and fuelled by high-nitrogen natural gas from the domestic Kościan–Brońsko fields. It was the largest energy facility of this type in western Poland based on domestic gas, producing electricity and heat in cogeneration. Construction of the block was a condition of the company's privatisation (privatisation agreement of 7 September 2001, under which the Minister of the State Treasury sold 45% of shares to a consortium of KOGENERACJA S.A. and Dalkia Termika S.A.). The general contractor, under a turnkey (EPC) formula, was a consortium of Elektrim-Megadex S.A. and Enprima Engineering Ltd. (Finland). The first foundations were laid on 21 August 2002, construction took two years, and operation began on 9 August 2004; ceremonies marking the block's start-up were held on 8 October 2004, and the block was taken into commercial operation from 1 October 2004. The main source of financing was a loan from a consortium of Pekao S.A. and PKO BP S.A. banks under the Credit Agreement of 30 April 2002 (a facility of approximately PLN 550 million was made available, of which PLN 505 million was drawn), and the Ekofundusz Foundation provided a grant of PLN 40 million to partially finance the purchase of the gas turbine unit. The total cost of the investment exceeded PLN 532 million. Gas is supplied from the Kościan–Brońsko field via a 100-kilometre high-pressure pipeline (an accompanying investment carried out and financed separately by PGNiG S.A.).
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- blok w eksploatacji od 9 sierpnia 2004 r.; komercyjna eksploatacja od 1 października 2004 r.
- Capacity or target
- 190 MWe / 95 MWt
Timeline
- Announced2001
- Construction start2002
- Delivery2004
Significance
The combined-cycle gas turbine block at the 'Zielona Góra' CHP plant was the largest energy investment in western Poland based on natural gas from domestic fields, and one of the first large combined-cycle gas turbine blocks in Poland fuelled by domestic gas. It made it possible to use high-nitrogen gas from the Kościan–Brońsko fields for the highly efficient cogeneration of electricity and heat, replacing coal-based generation and reducing emissions. Electricity is fed into the national transmission grid via a 220 kV line to the substation in Leśniów.
Sources 5 · 4 independent · 3 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Elektrociepłownia „Zielona Góra” S.A.2005StatusStageCostAnnouncedConstruction startDeliveryInvestorFundingUtilisation
Status · DeliveryRozpoczęcie eksploatacji nastąpiło 9 sierpnia 2004 roku.
Stage · Utilisationpodpisanie z PSE aneksu nr 5 do KDT wraz z załącznikami, w którym określono, że BGP został przyjęty do komercyjnej eksploatacji od 1 października 2004 r.
CostCałkowity koszt inwestycji budowy bloku gazowo-parowego w Elektrociepłowni „Zielona Góra” wyniósł ponad 532 miliony PLN.
AnnouncedSeptember 07th, 2001 - EC ZG Privatization Contract. The Minister of Sate Treasury sold 45% of shares to Zespół Elektrociepłowni Wrocławskich KOGENERACJA S. A. and Dalkia Termika S. A. The privatization process was conditioned by the implementation of the CCGT project.
Construction startAugust 21st, 2002 - first foundations stones were set
InvestorUmożliwiło to sprywatyzowanie spółki i pozyskanie od Inwestora - KOGENERACJI S. A. - środków własnych, niezbędnych do uzyskania kredytu inwestycyjnego.
FundingPodstawowym źródłem finansowania inwestycji przez Elektrociepłownię „Zielona Góra” był kredyt pozyskany od konsorcjum banków: Bank Polska Kasa Opieki S. A. i Powszechna Kasa Oszczędności Bank Polski S. A., w ramach Umowy Kredytu z 30 kwietnia 2002 r. Umowa Kredytu przewidywała udostępnienie kredytu w wysokości około 550 milionów PLN. Z kwoty tej wykorzystano 505 milionów PLN.
FundingW dniu 3 czerwca 2002 r. pomiędzy: Zespołem Elektrociepłowni Wrocławskich KOGENERACJA S.A., Dalkią Termiką S.A., Elektrociepłownią „Zielona Góra” S. A. i Bankiem Polska Kasa Opieki S. A. podpisano dwie Umowy Pożyczek Podporządkowanych na łączną kwotę prawie 70 milionów PLN, na okres od maja 2002 r. do końca 2018 r. Z powyższej kwoty 9,7 milionów PLN zostało przeznaczone na finansowanie inwestycji, a 60 milionów PLN stanowiło, i stanowić będzie, zabezpieczenie niezapłaconych rat kapitałowych kredytów i odsetek od nich należnych.
FundingW dniu 24 kwietnia 2003 r. podpisano z Fundacją Ekofundusz Umowę o udzieleniu dotacji na kwotę 40 milionów PLN na częściowe sfinansowanie zakupu turbozespołu gazowego. Była to największa w historii Ekofunduszu dotacja przeznaczona na pojedyncze przedsięwzięcie.
- Wikipedia (pl)
- PGE Energia Ciepła / Elektrociepłownia „Zielona Góra” S.A.
- [4]ZIELONA GÓRA: Elektrociepłownia ma 45 lat. Zwalcza smog. Rozbiera komin [WIDEO, ZDJĘCIA] ↗archived ✓Gazeta Lubuska22 Oct 2019StatusStageDelivery
Status · Stage · DeliveryPo 10 latach trudnych prac przygotowawczych oraz dwóch latach budowy, 8 października 2004 r. uroczyście uruchomiono nowoczesny blok gazowo-parowy o mocy elektrycznej 190 MWe i mocy cieplnej 95 MW zasilany gazem ziemnym z kopalni Kościan–Brońsko.
- Urząd Marszałkowski Województwa Lubuskiego (portal lubuskie.pl)17 Oct 2024DeliveryStatus
Delivery · StatusJednym z kluczowych wydarzeń dla elektrociepłowni było uruchomienie bloku gazowo-parowego w 2004 roku, który zastąpił blok węglowy.