Czorsztyn-Niedzica Hydropower Complex (dam and reservoir on the Dunajec)

completedstage: operationaldelayed

A hydrotechnical complex on the Dunajec River comprising the Czorsztyn-Niedzica dam and reservoir together with a pumped-storage hydropower plant and a smaller balancing weir at Sromowce Wyżne. Construction began in 1975, and work on the reservoirs, dams and power plant was completed in 1997, with a company established the same year to operate them. The Niedzica dam is Poland's highest earth-fill dam with a central clay core – its maximum height is 56 m and its length 404 m. The Niedzica power plant operates in a pumped-storage configuration (2×46.375 MW in turbine mode). The complex serves flood protection, energy and recreational functions, impounding the waters of the Dunajec and creating Lake Czorsztyńskie. The owner is Zespół Elektrowni Wodnych Niedzica S.A. – a wholly State Treasury-owned company.

How it went

Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, 2 have an assessment with no confirmed quote. How to read this section

Scheduledelayed[3]

Timeline

  1. Construction start1975
  2. Delivery1997

Change history

  • 1997status: completedCompletion of the reservoirs, dams and power plant, and establishment of the operating company.
  • 1997stage: operational
  • 1975stage: construction

Significance

The Czorsztyn-Niedzica complex of reservoirs and dams, completed in 1997 after more than two decades of construction, is one of the largest post-war hydrotechnical investments in Poland. The Niedzica dam – the country's highest earth-fill dam (56 m) – and the reservoir on the Dunajec perform a key flood protection function for the Dunajec valley, while the accompanying pumped-storage power plant supports the National Power System. The reservoir created Lake Czorsztyńskie, which has become an important element of water management and recreation in the region.

Sources 7 · 5 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusStageConstruction startInvestor
    Status · StageRealizację zbiorników, zapór oraz elektrowni zakończono w 1997.
    Construction startBudowę rozpoczęto w 1975.
    InvestorJest jednoosobową spółką Skarbu Państwa
  2. Wikipedia (pl)
    Delivery
    DeliveryRealizację zapory, zbiornika oraz elektrowni zakończono dopiero w 1997.
  3. Schedule
    ScheduleDwadzieścia trzy lata temu przekroczono pierwszy termin jej zakończenia. Potem ogłaszano nowe terminy. I znów je przekraczano.
  4. MuratorPLUS (Murator S.A.)17 Sep 2024
    DeliveryStatusStage
    Delivery · Status · StageZbiornik uruchomiony w 1997 roku, pojemność całkowita ok. 230 mln m³, powierzchnia 11 km², wysokość zapory 56 m, głębokość maksymalna 50 m (średnio ok. 19 m).
  5. MojePieniny.pl7 Jul 2026
    StatusDeliveryStage
    Status · Delivery · Stage29 lat temu, 9 lipca 1997 roku po 22 latach budowy nastąpiło otwarcie Zespołu Zbiorników Wodnych Czorsztyn – Niedzica (obecnie Zespół Elektrowni Wodnych Niedzica).
  6. WP Tech (Wirtualna Polska)17 Feb 2016
    StatusStage
    Status · StageElektrownia Wodna Niedzica jest wyposażona w dwie turbiny, które podczas pracy generują moc na poziomie 92 MW (łącznie).
  7. Do Rzeczy – Historia9 Jul 2026
    Construction start
    Construction startBudowę zespołu zbiorników, czyli głównego w Czorsztynie-Niedzicy oraz wyrównawczego w Sromowcach Wyżnych, rozpoczęto w 1975 roku.