Barrier on the Poland–Belarus border (physical barrier + electronic barrier)

completedstage: operationaldelivereddelayed
PLN 1.6 billion
programme budget (multi-year) · data from 15 Jun 2023net or gross: not recorded≈ PLN 1.6 billion (value-by-stage, est., nominal)funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A permanent security installation on the border with Belarus, built under a special act in force since 4 November 2021. It consists of a physical barrier – a 5.5 m high steel fence along 186 km of the border (contracts with Budimex and the Unibep/Budrex consortium signed on 4 January 2022, works from January 2022, original deadline 30 June 2022) – and an electronic barrier: a system of approximately 3 thousand day-night and thermal imaging cameras and 400 km of detection cables operating along 206 km of the border, whose formal acceptance was completed on 15 June 2023. The cost of the entire investment is approximately PLN 1.6 billion. In July 2024, modernisation contracts were signed: reinforcement of the physical barrier's spans (over PLN 117 million, Polimex Mostostal) and modernisation of the electronic barrier (over PLN 125 million, Telbud).

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduledelayed[6]
Utilisationin use[1]
operational coverage of the protected border (physical barrier + perimeter system)
Current
system perymetrii działa na całej długości granicy z Białorusią (206 km) plus 186 km stalowej zapory fizycznej; ok. 29,6 tys. wykrytych prób nielegalnego przekroczenia w 2025 r. (30,4 tys. w 2024 r.) (2023-06 to 2026)
Capacity or target
206 km (pełne pokrycie chronionego odcinka granicy)
Unit
km of border under surveillance

Timeline

Slip: +12 mo. vs. the original date

  1. AnnouncedNov 2021
  2. Construction startJan 2022
  3. Original date30 Jun 2022
  4. Last stated date15 Jul 2022
  5. Delivery15 Jun 2023

Change history

  • 15 Jun 2023stage: operational
  • Jan 2022stage: construction

Significance

The barrier is the main permanent security installation along the section of the border with Belarus guarded by the Podlaski Border Guard Regional Unit: 186 km of 5.5 m high steel fence is complemented by a perimeter system operating along 206 km of the border. The government presented the investment as an element of protecting NATO's eastern flank under conditions of migratory pressure from Belarus. The installation continues to be developed after completion (reinforcement of spans, modernisation of the camera system using alarm classification) and precedes a broader eastern border fortification programme (Tarcza Wschód).

Sources 11 · 9 independent · 11 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Straż Graniczna15 Jun 2023
    StatusStageDeliveryStage historySignificanceUtilisation
    Status · Delivery · Stage historyDzisiaj zakończył się formalny odbiór prac budowlanych przy instalacji bariery elektronicznej na granicy polsko-białoruskiej.
    Stage · UtilisationSystem perymetrii działa na całej długości granicy z Białorusią, tj. 206 kilometrach.
    Significance3 tysiące kamer dzienno-nocnych i termowizyjnych, 400 km kabli detekcyjnych oraz 11 kontenerów teletechnicznych
  2. PAP1 May 2023
  3. MSWiA / gov.pl4 Jan 2022
    Significance
    SignificanceZapora będzie miała długość ponad 186 km.
  4. PAP10 Jul 2024
    Description
    DescriptionPrzedmiotem umowy jest wzmocnienie przęseł bariery fizycznej. Wykonawcą jest Polimex Mostostal S.A. Na wykonanie zaplanowanych prac zakontraktowano kwotę ponad 117 mln zł. Termin realizacji - 11.2024 r.
    DescriptionUmowa ws. modernizacji zapory elektronicznej została podpisana w piątek w Komendzie Głównej SG z firmą Telbud SA. Wartość umowy to ponad 125,2 mln zł.
  5. money.pl16 Feb 2022
    LocationZapora zostanie zbudowana na odcinkach ochranianych przez Podlaski Oddział SG.
  6. PortalSamorzadowy.pl7 Jul 2022
    Original dateLast stated dateSchedule
    Original datePierwotnie zapora miała być skończona 30 czerwca.

    year taken from the source's publication date (7 Jul 2022)

    Last stated date · ScheduleDo 15 lipca jest przedłużony termin zakończenia budowy zapory na granicy polsko-białoruskiej

    year taken from the source's publication date (7 Jul 2022)

  7. Wikipedia
    CostAnnouncedConstruction startInvestorStage history
    CostKoszt przedsięwzięcia wyniósł 1 mld 615 mln zł[3].
    AnnouncedW dniu 29 października 2021[1] Sejm ostatecznie uchwalił rozpatrywaną w tzw. trybie pilnym ustawę o budowie zabezpieczenia granicy państwowej, która po podpisaniu przez prezydenta Andrzeja Dudę weszła w życie 4 listopada 2021 roku
    Construction start · Stage historyPierwsze prace budowlane rozpoczęto w styczniu 2022 roku[4].
    InvestorInwestorem był Komendant Główny Straży Granicznej.
  8. InfoSecurity2431 Dec 2025
    Utilisation
    Utilisationponad 29,6 tys. prób jej nielegalnego przekroczenia
  9. Forsal.pl5 Apr 2026
  10. TVN243 Jan 2024
  11. Funding
    FundingJej szacowny koszt w Ocenie Skutków Regulacji to 1 mld 615 mln zł. Wydatki zostaną pokryte z budżetu państwa. W skład tej kwoty wchodzi 1 mld 500 mln zł na budowę fizycznej bariery oraz 115 mln zł na urządzenia techniczne (perymetria).