Purchase of 32 AW149 helicopters (Perkoz programme)
The contract for 32 AW149 multirole helicopters for Land Forces aviation was signed on 1 July 2022 at PZL-Świdnik under the Perkoz programme. It also covers logistics and training-simulator packages. The contract is worth PLN 8.25 billion gross, with deliveries planned for 2023–2029. The first 10 machines were built in Italy and the remaining 22 are built in Świdnik. In November 2025 the first helicopter from the Polish production line went to the 25th Air Cavalry Brigade.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Construction startJul 2022
- Current date2029
Change history
- Oct 2023stage: commissioning
- Jul 2022stage: announced
Significance
According to Defence24 (2023), the AW149 is planned to replace at least the W-3 Sokół helicopters in the Air Cavalry. Setting up and launching a production line at PZL-Świdnik was part of the contract. According to the plant's president, full production capability was reached 20 months after signing.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- MILMAG1 Jul 2022CostConstruction startInvestor
CostWartość kontraktu wynosi 8,25 mld złotych brutto
Construction startzostała podpisana umowa na dostawę wielozadaniowych śmigłowców wsparcia typu AW149 dla Lotnictwa Wojsk Lądowych w ramach programu Perkoz.
InvestorStronami umowy są Skarb Państwa – Agencja Uzbrojenia oraz Wytwórnia Sprzętu Komunikacyjnego PZL-Świdnik.
- Defence2415 Dec 2023Current dateStage historySignificance
Current datea ostatnia maszyna ma zostać przekazana w roku 2029.
Stage historywojsko odebrało pierwsze dwa AW149 pod koniec października 2023 roku
SignificancePlanuje się, że przynajmniej te pierwsze zostaną zastąpione przez AW149.
- wnp.pl (PAP)27 Nov 2025StatusStageSignificance
Status · StageDo 25 Brygady Kawalerii Powietrznej trafił pierwszy wielozadaniowy śmigłowiec AW-149 z polskiej linii produkcyjnej.
StatusDotychczas 7 Dywizjonowi Lotniczemu 25 Brygady Kawalerii Powietrznej przekazano 11 śmigłowców AW-149.
SignificanceIstotną częścią kontraktu było utworzenie i uruchomienie linii produkcyjnej w PZL-Świdnik.
Significancepo 20 miesiącach w polskim zakładzie stworzono pełne zdolności produkcyjne