Waste Thermal Treatment Plant in Kraków (Ekospalarnia)
The Municipal Waste Thermal Treatment Plant in Kraków, known as Ekospalarnia, is a waste-to-energy facility located in the south-eastern part of the city, in the Nowa Huta district (District XVIII), at 23 Jerzego Giedroycia Street. The beneficiary and investor of the project was Krakowski Holding Komunalny S.A. w Krakowie (a municipal company owned by the City of Kraków). The construction contract was signed in 2012, construction works began on 6 November 2013, and the general contractor was the South Korean company POSCO Engineering & Construction Co. The facility was ultimately handed over to KHK S.A. for operation on 27 June 2016, and the physical scope of the project was completed on 30 November 2016. The total cost of the project was approximately PLN 666 million net (approximately PLN 819 million gross); co-financing from the Cohesion Fund under the Operational Programme Infrastructure and Environment (POIiŚ) amounted to approximately PLN 372 million (approximately 55.8% of eligible costs), and the investment was also supported by a preferential loan of PLN 293 million from NFOŚiGW (the National Fund for Environmental Protection and Water Management). The plant can process (recover) a stream of 220,000 tonnes a year of mixed municipal waste (up to a maximum of approximately 245,000 tonnes), providing, through cogeneration, recovery of the energy contained in the waste and production of electricity and heat (approximately 100,000 MWh of electricity a year). The plant uses modern equipment meeting Best Available Techniques (BAT) requirements.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- eksploatacja od 2016 r.
- Capacity or target
- 220 tys. ton odpadów komunalnych rocznie (maks. ok. 245 tys. ton)
Timeline
- Construction start6 Nov 2013
- Delivery2016
Significance
Ekospalarnia is the largest municipal waste thermal treatment facility in the Małopolskie region, and one of six so-called large waste incineration plants built in Poland with EU co-financing under the 2007–2013 financial perspective. The plant closed a gap in Kraków's waste management system, enabling the energy recovery of approximately 220,000 tonnes of mixed municipal waste a year instead of landfilling it, along with the cogenerated production of electricity and heat.
Sources 4 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Krakowski Holding Komunalny S.A.CostInvestorFunding
CostCałkowity koszt realizacji Projektu wyniósł ok. 666 mln zł netto (ok. 819 mln zł brutto).
InvestorKrakowski Holding Komunalny S.A. w Krakowie (Beneficjent projektu).
FundingDofinansowanie ze środków Funduszu Spójności udzielone na realizację Projektu wyniosło ok. 372 mln zł (czyli ok. 55,8% kosztów kwalifikowanych)
FundingWkład własny KHK S.A. w kwocie ok. 294 mln zł został pokryty ze środków własnych i pożyczki z NFOŚiGW na kwotę 293 mln zł udzielonej na zasadach preferencyjnych.
FundingWkład własny KHK S.A. w kwocie ok. 294 mln zł został pokryty ze środków własnych
- Krakowski Holding Komunalny S.A.StatusStageDelivery
Status · Stage · Deliveryostatecznie obiekt przekazano KHK S.A. do eksploatacji 27 czerwca 2016 roku.
- Inżynier Budownictwa11 Dec 2015Construction start
Construction startRoboty budowlane rozpoczęły się 6 listopada 2013 r.
- Magazyn BiomasaUtilisation
UtilisationPrzyniosło je podsumowanie roku działalności Ekospalarni, do której trafia trzy czwarte śmieci wytworzonych przez mieszkańców Krakowa