Expansion of the Warsaw Energy Plant (ITPOK, formerly ZUSOK) in Targówek

completedstage: operational
PLN 1.7 billion
contract value · data from 2020net or gross: not recorded≈ PLN 1.7 billion (value-by-stage, est., nominal)funding: private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Expansion and modernization of the Municipal Solid Waste Disposal Plant (ZUSOK) in Warsaw's Targówek district, renamed the Warsaw Energy Plant (WWE). The implementation contract with the Korean company POSCO Engineering & Construction was signed in 2020, work began in 2021, and the expanded installation was commissioned in February 2026. After the expansion, it is the largest thermal municipal waste treatment installation in Poland, belonging to the Municipal Cleaning Company in the Capital City of Warsaw (MPO).

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 2 years: originally 2023, currently 2026-02.

Timeline

  1. Announced2020
  2. Construction start2021
  3. Original date2023
  4. DeliveryFeb 2026

Change history

  • Feb 2026status: completedCommissioning and official opening of the Warszawska Wytwórnia Energii.
  • Feb 2026stage: operational
  • 2021status: in progressStart of construction work on the expansion of ZUSOK.
  • 2021stage: construction

Significance

The plant can process approx. 265 thousand tons of mixed municipal waste per year, converting it into electricity and heat supplying Warsaw's networks. The value of the contract with the general contractor amounted to approx. PLN 1.668 billion net (nearly PLN 2.05 billion gross). The investment, originally planned for completion in 2023, incurred a delay of several years and only started up in 2026.

Sources 7 · 4 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. MPO Warszawa30 Nov 2020
    InvestorOriginal date
    InvestorMiejskim Przedsiębiorstwem Oczyszczania w m.st. Warszawa (MPO)
    Original dateZakładamy, że zakończenie budowy i rozruch rozbudowanego zakładu nastąpi w roku 2023
  2. PortalSamorzadowy.plFeb 2026
    Announced
    AnnouncedUmowę na budowę prezydent Rafał Trzaskowski podpisał 30 listopada 2020 r.
  3. PortalSamorzadowy.pl
    CostSignificance
    CostSpalarnia, w chwili podpisywania umowy miała kosztować prawie 2 mld zł brutto (ok. 1 mld 667 mln zł netto)
    SignificanceWarszawska Wytwórnia Energii MPO Warszawa będzie największą w Polsce instalacją termicznego przekształcania odpadów komunalnych. Dzięki finalizowanej obecnie rozbudowie zakład zwiększy swoją przepustowość, dzięki czemu będzie przetwarzać ok. 265 tys. ton odpadów komunalnych w skali roku
  4. Wikipedia
    StageConstruction startDeliveryStage history
    NameWarszawska Wytwórnia Energii (WWE)[1], do 2025 roku Zakład Unieszkodliwiania Stałych Odpadów Komunalnych (ZUSOK) – spalarnia odpadów znajdująca się przy ulicy Gwarków 9, w dzielnicy Targówek w Warszawie.
    Stage · DeliveryZakład został uruchomiony w lutym 2026 roku
    Construction startPrace rozpoczęły się w 2021
    Delivery · Stage historyZakład został uruchomiony w lutym 2026 roku[3].
    Location52,261588°N 21,103369°E
    Locationprzy ulicy Gwarków 9, w dzielnicy Targówek w Warszawie
    NameW 2020 podpisano umowę na rozbudowę spalarni z koreańską spółką POSCO Engineering & Construction Co. Ltd., która złożyła ofertę o wartości 1,668 mld zł[11].
  5. Funding
    FundingUmowa pomiędzy Miejskim Przedsiębiorstwem Oczyszczania w m.st. Warszawie a Bankiem Pekao S.A. i PEKAO TFI S.A. została podpisana.
  6. Urząd m.st. Warszawy19 Feb 2026
    StatusStageDescription
    Status · StageWarszawska Wytwórnia Energii jest już oficjalnie otwarta.
    DescriptionTo jeden z najnowocześniejszych zakładów tego typu w Europie oraz największa taka instalacja w Polsce.