← all projects
Energystrategic

FSRU Terminal in the Gulf of Gdańsk (FSRU Programme)

under construction stage: construction
4.5 bn PLN
programme budget (multi-year) · data from May 2025 ≈ 4.5 bn PLN (value-by-stage, est., nominal)

The FSRU Programme, carried out by Gaz-System, comprises the construction of a floating LNG regasification terminal in the Gulf of Gdańsk, in the area of Górki Zachodnie in Gdańsk, and the expansion of the national transmission network by approx. 250 km of gas pipelines (including Gdańsk–Gustorzyn). The chartered FSRU unit, with tank capacity of 170,000 m3 of LNG, is to enable the receipt and regasification of at least 6.1 billion m3 of gas per year. The onshore part of the programme was planned for completion in 2026, the regasification unit was launched in May 2026 at the HD Hyundai Heavy Industries shipyard in South Korea, its arrival in the Gulf of Gdańsk is envisaged for the end of 2027, and the start of regasification services for the first quarter of 2028. The estimated cost of the offshore and onshore infrastructure is approx. PLN 4.5 billion (excluding the cost of chartering the unit).

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial

Timeline

  1. Construction start 2025
  2. Current date 2028

Change history

  • May 2026 stage: construction

Significance

The terminal is to increase Poland's liquefied natural gas import capacity and strengthen the diversification of supplies. The target regasification capacity of at least 6.1 billion m3 of gas per year is to cover a significant part of national demand.

Sources 4 · 3 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Gaz-System S.A.
    DescriptionConstruction start
    Construction start „Rozpoczęcie prac budowlanych związanych z powstaniem nabrzeża i gazociągu podmorskiego jest planowane w 2025 roku"
  2. WNP.pl 31 May 2025
    Cost
    Cost „Ta kwota nie uwzględnia zakupu jednostki, ponieważ będzie ona przez nas czarterowana"
  3. Gaz-System S.A. 19 May 2026
    StatusStageStage historyCurrent dateSignificance
    Status „W maju w południowokoreańskiej stoczni HD Hyundai Heavy Industries zwodowano jednostkę regazyfikacyjną FSRU"
    Current date „rozpoczęcie świadczenia usług regazyfikacji planowane jest na pierwszy kwartał 2028 roku"
  4. Bankier.pl 23 Oct 2025
    InvestorCurrent date
    Investor „Operator sieci przesyłowej Gaz-System poinformował, że prace przy budowie polskiego terminala gazowego FSRU nabierają tempa."
    locations „gazociąg podmorski, po wyjściu na ląd w Górkach Zachodnich połączony zostanie z nowo wybudowanym gazociągiem Gdańsk-Gustorzyn"