The Paediatric Hospital of the Medical University of Warsaw at Żwirki i Wigury 63A was built on the Banacha Campus to replace the previous sites on Marszałkowska and Działdowska streets. Warbud was the general contractor and the design came from the Open Architekci studio. Construction began in September 2011 and finished in January 2015, and the hospital was officially handed over for use at the end of September 2015. The investment, financed from the state budget, cost about PLN 550 million.
How it went
No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
Timeline
- Construction startSep 2011
- DeliverySep 2015
Change history
- Sep 2015stage: operational
Significance
The hospital has 535 beds for young patients, 156 more than the previous sites. The complex has seven storeys above ground and one below, a usable floor area of 40,018 m² and a helipad for the Air Ambulance Service on the roof. After the opening, concerns were raised about the ambulance entrances and the number of parking spaces.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Muratorplus2 Oct 2015StatusStageCostConstruction startDeliveryInvestor
Status · Stage · DeliveryZ końcem września 2015 szpital został oficjalnie oddany do użytku.
CostKoszt inwestycji wyniósł około 550 mln zł.
Construction startBudowa rozpoczęła się we wrześniu 2011, a ukończona została w styczniu 2015.
InvestorOdbyło się już oficjalne otwarcie Szpitala Pediatrycznego, inwestycji Warszawskiego Uniwersytetu Medycznego.
- Menedżer Zdrowia (termedia.pl)19 Jan 2016Funding
FundingPowstanie nowego gmachu było finansowane z budżetu państwa.
- Rynek Zdrowia7 Sep 2011