PGE has commissioned the consortium of Polimex Mostostal (consortium leader) and Siemens Energy to build two peaking gas-fired power plants: in Rybnik (Śląskie Voivodeship) and in Gryfino/Nowe Czarnowo at the Dolna Odra Power Plant (Zachodniopomorskie Voivodeship). Each unit has a capacity of approx. 600 MW (nearly 1.2 GW in total) and will be built using open-cycle gas turbine (OCGT) technology – as so-called peakers, started up quickly during peak demand and to balance renewable energy sources. The combined value of both contracts, including servicing, is approx. PLN 6 billion. In December 2025, both units secured 15-year contracts in the capacity market auction for the years 2030–2044, and the construction order was announced in March 2026. These are units separate from the combined-cycle gas units (CCGT) already operating on the same sites – Nowy Rybnik 882 MW and Dolna Odra 2x approx. 700 MW.
How it went
No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
Timeline
- AnnouncedDec 2025
- Original date2030
- Current date2030
Change history
- Mar 2026stage: tender
- Dec 2025stage: announced
Significance
The peaking OCGT units are to supply flexible, quickly dispatchable power supporting the National Power System during periods of increased demand and balancing the growing share of non-controllable renewable sources. The investment fits into the move away from coal – it is to replace part of the worn-out coal capacity – and secures energy supplies during the transition period, complementing the combined-cycle gas units already operating on both sites.
Sources 7 · 6 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- WNP.plMar 2026
- Rzeczpospolita (energia.rp.pl)Mar 2026
- Energetyka24Mar 2026CostOriginal dateCurrent dateDescription
CostWartość obu inwestycji, łącznie z 12-letnim serwisem, to około 6 mld zł.
Original date · Current dateInwestycje mają zostać ukończone do 2030 r.
DescriptionProjekty o mocy ok. 600 MW każdy zrealizuje konsorcjum firm w składzie: Polimex Mostostal S.A., jako lider konsorcjum, Siemens Energy sp. z o.o., Siemens Energy Global GmbH & Co. KG
- Bankier.plMar 2026Description
DescriptionMówimy o projektach o łącznej mocy blisko 1200 MW
- 24Kurier.plMar 2026StatusStageCostInvestorAnnouncedStage historyDescriptionFunding
Status · Announced · Stage history · FundingW grudniu 2025 r. oba zamawiane bloki uzyskały 15-letnie kontrakty w aukcji rynku mocy, kontraktując moc 1097,718 MW na 15 lat, na lata 2030-44.
Stage · Investor · Stage historyGrupa PGE zamówiła w środę u konsorcjum Polimex Mostostal i Siemens Energy budowę szczytowych bloków
CostŁączna wartość obu kontraktów, razem z serwisem, to ok. 6 mld zł.
Locationszczytowych bloków w Rybniku i Gryfinie (Dolna Odra) o mocy ok. 600 MW każdy
DescriptionOba bloki szczytowe, określane potocznie jako peakery, powstaną w technologii otwartego cyklu spalania (OCGT).
- PGE Polska Grupa EnergetycznaMar 2026