SwePol Link – Poland–Sweden HVDC submarine power cable

completedstage: operationaldelivered
SEK 2.7 billion
estimate · data from 2000net or gross: not recorded≈ PLN 1.0 billion (value-by-stage, est., nominal)funding: foreign loanLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

SwePol Link is a cross-border, submarine high-voltage direct-current (HVDC) power connection linking the electricity systems of Poland and Sweden. The line can transmit 600 MW of power at 450 kV, and its total length is approximately 254 km, of which 238 km runs under the seabed of the Baltic Sea. The cable runs between the Stärnö peninsula near Karlshamn in Sweden and the locality of Wierzbięcin near Słupsk in Poland, where its submarine section ends at the Słupsk substation. The investor was SwePol Link AB, a company whose shareholders were the Swedish transmission operator Svenska Kraftnät, the Vattenfall group, and Polskie Sieci Elektroenergetyczne (the Polish power grid company). The HVDC converter technology and the cable were supplied by ABB (a 1997 order worth approximately USD 260 million). The line was commissioned in 2000 after roughly a year and a half of construction (commercial operation began in August 2000). The estimated cost of building the connection was approximately SEK 2.7 billion. In August 2012, the assets of the SwePol Link companies were sold to the national transmission operators: the Polish part went to PSE and the Swedish part to Svenska Kraftnät, after which it was integrated into the respective national transmission networks.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[4]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

eksploatacja transgranicznego interkonektora HVDC 600 MW
Current
połączenie czynne, oddane do użytku w 2000 r.; polska część zintegrowana z siecią PSE (2026)
Capacity or target
600 MW

Timeline

  1. Delivery2000

Significance

SwePol Link was the first direct-current (HVDC) submarine connection between the Polish power system and a foreign country, and one of the first cross-border interconnectors linking Poland with the Scandinavian market. It enabled two-way exchange of electricity of up to 600 MW between Poland and Sweden, increasing supply security and integration with the Nordic market. The Polish part of the connection is today part of the national transmission network managed by PSE.

Sources 5 · 3 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusCostDelivery
    Status · DeliveryLinia SwePol została oddana do użytku w roku 2000 po półtorarocznej budowie
    CostSzacowany koszt powstania to 2,7 miliarda SEK
  2. Polskie Sieci Elektroenergetyczne (PSE)
    Investor
    InvestorJej inwestorem była spółka SwePol Link AB.
  3. Wikipedia (en)
  4. Hitachi Energy (dawniej ABB)
    StageUtilisation
    Stage · UtilisationSwePol began commercial operations in August 2000
  5. Funding
    FundingRegeringen har gett Riksgälden i uppdrag att garantera ett nytt lån till SwePol Link AB. Lånet ska användas till att återbetala nuvarande lån från en av ägarna, Vattenfall AB.