Siarzewo Barrage on the Vistula

pausedstage: permitsdelayed
7.5 bn PLN
programme budget (multi-year) · data from 10 Oct 2023net or gross: not recorded≈ 7.5 bn PLN (value-by-stage, est., nominal)funding: state budget (multi-year programme "Development of the Lower Vistula")

A planned barrage on the Vistula in the locality of Siarzewo below Włocławek (Kujawsko-Pomorskie Voivodeship): a dam with a navigation lock, a reservoir with a capacity of 135 million m3, and a hydroelectric power plant with a capacity of approx. 80 MW. The investor is PGW Wody Polskie, and financing of over PLN 7.5 billion was provided for in the multi-year programme "Development of the Lower Vistula" adopted in October 2023. Following the annulment of the environmental decision by the GDOŚ in December 2024 and the dismissal of Wody Polskie's appeal by the Provincial Administrative Court in Warsaw in June 2026, the investment remains blocked; Wody Polskie announce a cassation appeal to the Supreme Administrative Court (NSA).

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverynot delivered[3]
Scheduledelayed[1]
Utilisationnot operational[4]
construction not started (blocked at the environmental decision stage)
Current
0 (2026-06)
Capacity or target
80 MW / 135 mln m3
Unit
MW / m3

Timeline

Slip: about 7 years vs. the original date (given as a year)

  1. Announced2017
  2. Original date2025
  3. Current date2032

Change history

  • 2017stage: permits

Significance

The barrage was to increase annual electricity production by approx. 350 GWh, improve navigation conditions on the lower Vistula, and support flood protection below the dam at Włocławek. The project, whose concepts date back to the 1990s, has for years drawn opposition from scientists and environmental organizations pointing, among other things, to its impact on Natura 2000 areas and the Kulin reserve; the dispute over the environmental decision halted the investment before construction began.

Sources 7 · 7 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. TVN2410 Oct 2023
    CostAnnouncedOriginal dateCurrent dateInvestorSchedule
    CostNa realizację inwestycji rząd przeznaczy ponad 7,5 mld zł
    Announced · Original dateResort środowiska pod koniec 2017 roku informował, że budowa stopnia Siarzewo ruszy w 2020 roku, a zakończy się w 2025 roku.
    Current date · ScheduleZgodnie z zapowiedziami w ramach programu do 2032 roku ma zostać zrealizowana budowa stopnia wodnego poniżej Włocławka w miejscowości Siarzewo
    InvestorMinisterstwo Infrastruktury podało, że inwestorem zadania jest Państwowe Gospodarstwo Wodne Wody Polskie.
    LocationDokument zakłada finansowanie budowy stopnia wodnego na Wiśle na wysokości miejscowości Siarzewo w województwie kujawsko-pomorskim.
  2. OKO.press11 Oct 2023
  3. Portal Kujawski23 Jun 2026
    StageDelivery
    StageGeneralna Dyrekcja Ochrony Środowiska uchyliła decyzję środowiskową
    DeliveryW grudniu 2024 roku Generalna Dyrekcja Ochrony Środowiska uchyliła decyzję środowiskową I instancji. Od tego momentu przyszłość inwestycji stanęła pod dużym znakiem zapytania. Wody Polskie poszły z tym do sądu, ale w ubiegły piątek przegrały.
  4. Money.pl30 Jun 2026
    StatusUtilisation
    StatusSąd skargę oddalił i utrzymał w mocy decyzję o odmowie określenia środowiskowych uwarunkowań.
    UtilisationSąd skargę oddalił i utrzymał w mocy decyzję o odmowie określenia środowiskowych uwarunkowań
  5. Polskie Radio PiK2 Jul 2026
    Status
    StatusPod koniec czerwca Wojewódzki Sąd Administracyjny w Warszawie utrzymał wcześniejszą odmowę wydania decyzji środowiskowej na realizację tej inwestycji.
  6. Dziennik Gazeta PrawnaJun 2026
  7. Funding
    FundingNa realizację inwestycji rząd przeznaczy ponad 7,5 mld zł.