National Stadium (PGE Narodowy) in Warsaw

completedstage: operationaldelivereddelayedover budget
PLN 2.0 billion
contract value · data from 2013net or gross: not recorded≈ PLN 2.0 billion (value-by-stage, est., nominal)funding: state funds, state special fund, local governmentLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A multifunctional national stadium in Warsaw's Praga-Południe district, at al. ks. J. Poniatowskiego, built as a State Treasury investment for the UEFA Euro 2012 European Football Championship. Construction began on 7 October 2008, and the official inauguration of the facility took place on 29 January 2012. The stands hold over 58,000 seats for matches, and in a concert configuration the arena can accommodate even around 80,000 people. The construction cost was given as PLN 1,976,061,375 (excluding land and compensation, as of 2013). Since 1 January 2013 the operator has been the company PL.2012+, wholly owned by the State Treasury; since July 2015 the facility has operated under the sponsorship name PGE Narodowy.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. How to read this section

Deliverydelivered[1]
Scheduledelayed[3]
Budgetover budget[3]
Utilisationin use[5]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

annual number of visitors vs matchday capacity
Current
ponad 2 mln odwiedzających rocznie (2025)
Capacity or target
58 500 miejsc na mecz (do ~80 000 na koncert)
Unit
people

Timeline

Slip: +7 mo. vs. the original date

  1. Construction start7 Oct 2008
  2. Original date30 Jun 2011
  3. Delivery29 Jan 2012

Change history

  • 29 Jan 2012stage: operational
  • 7 Oct 2008stage: construction

Significance

The National Stadium was the largest single investment in an entertainment and sports facility in Poland's history, carried out for the needs of UEFA Euro 2012 – the tournament co-hosted by Poland and Ukraine. After the championship ended, the arena became the country's main multifunctional venue, hosting national team matches, concerts, and mass events for tens of thousands of spectators. Maintaining the facility also involved operating costs: in November 2022 a defect was detected in one of the elements of the steel-cable roof structure, due to which the stadium was temporarily closed, with reopening taking place in December 2022.

Sources 8 · 6 independent · 7 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. PGE Narodowy (PL.2012+)
    StatusStageConstruction startDeliveryStage historyInvestor
    Status · Stage · DeliveryOficjalna inauguracja miała miejsce 29 stycznia 2012 roku
    Construction start · Stage historyBudowa rozpoczęła się 7 października 2008 roku.
    InvestorOd 1 stycznia 2013 roku rola operatora obiektu została powierzona spółce PL.2012+, której właścicielem jest Skarb Państwa.
    InvestorW celu zbudowania kompleksu sportowego na terenach Stadionu Dziesięciolecia i zarządzania obiektami wchodzącymi w jego skład, zostało powołane Narodowe Centrum Sportu.
    Stage historyOficjalna inauguracja miała miejsce 29 stycznia 2012 roku, a miesiąc później, na murawie stadionu, rozegrane zostało pierwsze towarzyskie spotkanie pomiędzy Polską a Portugalią, które zakończyło się bezbramkowym remisem.
  2. PortalSamorzadowy.pl
    Cost
    CostWedle danych nadzorującej budowę stadionu i jego operatora spółki Narodowe Centrum Sportu budowa kosztowała ponad 1,976 mld zł – pisze „Gazeta Wyborcza”.
  3. Wikipedia (pl)
    Original dateCostScheduleBudget
    Original datePoczątkowo planowano zakończenie prac na 30 czerwca 2011.
    CostKoszt budowy 1 976 061 375 zł[2] bez gruntu i kwot odszkodowań (stan na 2013 r.)
    Locational. ks. J. Poniatowskiego 1 03-901 Warszawa
    SchedulePoczątkowo planowano zakończenie prac na 30 czerwca 2011
    Scheduleimprezę zaś przeniesiono na styczeń 2012
    ScheduleUkrywane problemy z budową schodów zostały ujawnione w maju 2011 r. i spowodowały opóźnienie w budowie o 3 miesiące.
    BudgetWedług pierwotnego kosztorysu inwestorskiego stadion miał kosztować 1 569 370 000 zł[60], jednakże koszty lawinowo rosły i stadion według informacji rządowych kosztował 1 976 061 375
  4. Rzeczpospolita (rp.pl)Dec 2022
  5. SportMarketing.plMay 2026
    Utilisation
    UtilisationW ubiegłym roku stadion odwiedziły ponad 2 miliony osób
  6. kspppn.pl
  7. Funding
    Fundingbyć sfinansowany ze środków budżetu państwa oraz Funduszu Rozwoju Kultury Fizycznej, ewentualnie Totalizatora Sportowego, czy Unii Europejskiej (około 80% kosztów inwestycji miał pokryć rząd).
  8. Funding
    Fundingw przypadku Stadionu Narodowego ziemia pod stadion została przekazana przez miasto za darmo