Poznań Stadium (redevelopment for UEFA Euro 2012)
A thorough redevelopment of the municipal stadium at ul. Bułgarska in Poznań, carried out as an investment of the City of Poznań for the UEFA Euro 2012 European Football Championship. As part of the modernization (the construction period of the new stadium being 2003–2010), four roofed stands were built; work on stands I and III lasted from October 2008 and was completed in September 2010. The official opening of the modernized facility took place on 20 September 2010. The capacity is 42,837 seats (increased to 43,269 from 2012). The construction cost of the new stadium was given as PLN 747 million. The owner is the City of Poznań (POSiR).
How it went
Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, 2 have an assessment with no confirmed quote. How to read this section
Timeline
Change history
- 20 Sep 2010stage: operational
- Oct 2008stage: construction
Significance
The redevelopment of the Municipal Stadium at ul. Bułgarska was one of Poznań's key investments connected with Poland's co-hosting of the UEFA Euro 2012 European Football Championship. In 2012, three group-stage matches of the tournament were played at the stadium. The facility remains the home stadium of the KKS Lech Poznań club and the city's main multifunctional sports and entertainment arena, holding over 42,000 spectators. The inaugural opening of the modernized stadium on 20 September 2010 was marked by a concert.
Sources 4 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Wikipedia (pl)StatusStageCostConstruction startDeliveryInvestor
Status · Delivery20 września 2010 odbyło się oficjalne otwarcie stadionu
StageW 2012 odbyły się na stadionie 3 mecze fazy grupowej Euro 2012
CostKoszt budowy nowy stadion – 747 mln zł
Construction startData budowy 1968–1980 (stary stadion) 2003–2010 (nowy stadion)
InvestorWłaściciel Miasto Poznań, POSiR
- muratorplus.pl31 Jan 2012
- tenpoznan.pl10 Oct 2023Budget
BudgetStadion został jednak ukończony w 2010 roku – jako pierwszy ze stadionów budowanych na Euro 2021 w Polsce – kosztował ostatecznie około 700 mln zł, znacznie więcej niż zakładało miasto na początku, i mieścił 43 tys. widzów.
- Funding
FundingPremier Donald Tusk zapewnił wczoraj prezydentów miast organizatorów piłkarskich mistrzostw Europy 2012, że budowa stadionów w Gdańsku, Wrocławiu i Poznaniu będzie współfinansowana z budżetu państwa.