Expansion of the Production Capacity of Huta Stalowa Wola (Krab/Borsuk/Rak)
A programme to expand and modernise the production capacity of Huta Stalowa Wola S.A. (PGZ Group), comprising the construction and expansion of production halls and the purchase of machinery in order to increase production of Polish land systems: the Borsuk infantry fighting vehicle, the Krab self-propelled howitzers, the Rak self-propelled mortars, and tracked chassis for the K9 self-propelled howitzer. The total value of the capital expenditure has been set at PLN 1,371.8 million, of which PLN 1,242.0 million comes from the Capital Investment Fund and PLN 105.8 million constitutes the company's own contribution. The company received the first tranche of funding, amounting to PLN 600 million, in June 2023, with further funds being transferred in 2025-2026. Expansion of the main hall is under way at the primary plant in Stalowa Wola; according to the company's declarations, production capacity is to increase threefold, and the entire investment is to be completed by 2030.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Construction startJun 2023
- Current date2030
Change history
- Mar 2025stage: construction
Significance
The investment is intended to increase the country's production capacity for key land systems for the Polish Armed Forces several times over, including the amphibious Borsuk infantry fighting vehicles (ultimately up to 100 units per year) and the Krab self-propelled howitzers (up to 50 units per year). This strengthens the PGZ Group's capacity to fulfil large arms contracts and reduces dependence on foreign manufacturers for armoured equipment supplies.
Sources 5 · 4 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Huta Stalowa Wola S.A.CostConstruction startFunding
CostŁączna wartość nakładów inwestycyjnych wyniesie 1.371,8 mln zł
Construction startW czerwcu 2023 r. Spółka otrzymała na realizację projektu inwestycyjnego I transzę dofinansowania w wysokości 600.000.000 zł
FundingŁączna wartość nakładów inwestycyjnych wyniesie 1.371,8 mln zł, w tym 1.242,0 mln zł ze środków Funduszu Inwestycji Kapitałowych oraz 105,8 mln zł wkładu własnego HSW S.A.
Funding105,8 mln zł wkładu własnego HSW S.A.
- ZBiAMJun 2023Investor
Investornależącej do Polskiej Grupy Zbrojeniowej, Hucie Stalowa Wola S.A.
- Defence2415 Feb 2023
- Polska Zbrojna28 Mar 2025StatusStageStage historyCurrent date
Status · Stage · Stage history · LocationNa terenie głównego zakładu spółki w Stalowej Woli trwa rozbudowa hali głównej do czterech naw o łącznej powierzchni 15 tys. mkw.
Current dateWszystkie zaplanowane inwestycje na łączną kwotę około 1,2 mld zł mają zostać zrealizowane do 2030 roku.
- ZBiAM15 Apr 2025