Reconstruction of the Silesian Stadium in Chorzów (2009–2017)

completedstage: operationaldelivereddelayedover budget
PLN 650 million
programme budget (multi-year) · data from 2017net or gross: not recorded≈ PLN 650 million (value-by-stage, est., nominal)funding: local government, state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A thorough reconstruction and modernisation of the historic Silesian Stadium in Chorzów (known as the Kocioł Czarownic, or Witches' Cauldron), a heritage-listed national stadium owned by the Silesian Voivodeship self-government (Urząd Marszałkowski Województwa Śląskiego). The stadium had been closed since autumn 2009, when the final stage of modernisation began, chiefly involving installation of the roof's cable structure. The main works were halted in July 2011 following a failure while raising the roof's cable structure: in 2011 one of the structural elements, known as the krokodyl (crocodile), responsible for the stability of the roof covering, which weighed over 220 tonnes, cracked, substantially delaying completion of the investment. The final cost of the modernisation came to approximately PLN 650 million. The new stadium, with a capacity of 54,378 seats, opened on 1 October 2017. The venue hosts matches of the Poland national football team, among other uses.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. How to read this section

Deliverydelivered[1]
Scheduledelayed[1]
Budgetover budget[1]
Utilisationin use[2]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

pojemność stadionu po przebudowie
Current
54 378 miejsc siedzących; obiekt czynny i wykorzystywany m.in. na mecze reprezentacji Polski (2017)
Capacity or target
54,378 miejsca siedzące

Timeline

  1. Construction start2009
  2. Delivery1 Oct 2017

Significance

The reconstruction brought back into use one of the most recognisable national stadiums in Poland, the historic Kocioł Czarownic (Witches' Cauldron), as a modern venue for more than 54,000 spectators, owned by the Silesian Voivodeship self-government. Since reopening in 2017 the stadium has served as one of the venues of the Poland national football team and as a site for major sporting and cultural events in the region.

Sources 6 · 4 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. PortalSamorzadowy.pl18 Sep 2017
    CostConstruction startDeliveryScheduleBudget
    CostOstateczny koszt modernizacji Śląskiego powinien zamknąć się ok. 650 mln zł.
    Construction startStadion Śląski był zamknięty od jesieni 2009 r., kiedy rozpoczął się końcowy etap jego modernizacji
    DeliveryStadion Śląski jest wreszcie gotowy. Trwająca od ośmiu lat modernizacja obiektu dobiegła końca, co oznacza, że stadion rozpoczyna swoją działalność.
    ScheduleZasadnicze prace wstrzymano w lipcu 2011 r. z powodu awarii przy podnoszeniu linowej konstrukcji dachu. Ostatecznie montaż zadaszenia zakończył się powodzeniem w grudniu 2015 r.
    BudgetOstateczny koszt modernizacji Śląskiego powinien zamknąć się ok. 650 mln zł. O zwiększonym wobec zakładanego koszcie zdecydowały głównie awaria przy budowie dachu i decyzja o rozszerzeniu funkcji obiektu.
  2. Wikipedia (pl)
    StatusStageDeliveryInvestorUtilisation
    Status · DeliveryPrzebudowę zakończono latem 2017, a nowy stadion otwarto 1 października 2017
    StagePo przebudowie pojemność stadionu została określona na 54 378 miejsc siedzących.
    InvestorWłaściciel Urząd Marszałkowski Województwa Śląskiego
    UtilisationOd sezonu 2023/2024 rozgrywa na nim swoje domowe mecze Ruch Chorzów
  3. Sztuka Architektury
  4. Funding
    FundingModernizacja obiektu w sumie kosztować będzie budżet województwa blisko 600 mln zł.
  5. Funding
    FundingWojewództwo Śląskie otrzymało z Ministerstwa Sportu i Turystyki 110 mln zł na dokończenie modernizacji Stadionu Śląskiego w Chorzowie, w tym głównie na budowę zadaszenia widowni i budowę parkingów.
  6. Boiska i Stadiony23 Feb 2018
    Delivery
    DeliveryOficjalne otwarcie nowo zmodernizowanego obiektu odbyło się 1 października 2017 r.