PUM Clinical, Teaching and Research Centre at University Clinical Hospital No. 1 in Szczecin

under constructionstage: construction
PLN 813 million
programme budget (multi-year) · data from 2025net or gross: not recorded≈ PLN 813 million (value-by-stage, est., nominal)funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Clinical, Teaching and Research Building of the Pomeranian Medical University (PUM) is the largest investment in the university's history, being built on ul. Unii Lubelskiej in Szczecin, opposite University Clinical Hospital No. 1. The facility, with a usable area of approximately 49,000 m², will house sixteen clinical and teaching units, including the Centre for Translational Medicine and the Collegium Pharmaceuticum, along with 49 teaching and lecture rooms, an auditorium for more than 400 people, and an underground garage for approximately 600 spaces. The investment is being carried out under the Multi-Year Program 2019-2026, and its total value is PLN 812,742,418, with co-financing from the Ministry of Health of PLN 802,098,000. Construction began at the end of 2023; the general contractor is a consortium of Korporacja Budowlana DORACO (leader) and PORR; the value of the construction works contract reached nearly PLN 519.8 million gross. The topping-out ceremony was held on 10 September 2025, and the facility is planned to be handed over for use in 2026, with full commissioning in the 2027/2028 academic year.

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Construction start2023
  2. Original date2026
  3. Current date2026

Change history

  • 10 Sep 2025stage: construction
  • Dec 2023stage: construction

Significance

Described as the largest investment in the history of the Pomeranian Medical University, it is intended to consolidate the university's dispersed clinical, teaching and research activities in a single modern complex with an area of approximately 49,000 m². The building will house sixteen organizational units, including the Centre for Translational Medicine and the Collegium Pharmaceuticum, 49 teaching and lecture rooms, and an auditorium for more than 400 people, strengthening the base for training medical personnel and scientific research in the West Pomeranian region. Located opposite University Clinical Hospital No. 1, the facility is to be handed over for use in 2026 and reach full operation in the 2027/2028 academic year.

Sources 4 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Nauka w Polsce (PAP)10 Sep 2025
    CostStatusStageStage historyConstruction startFunding
    Costcałkowita wartość inwestycji to 812 742 418 zł
    Status · Stage history · Construction startJego budowa rozpoczęła się pod koniec 2023 r.

    The source gives “towards the end of 2023”; the card reads a period as its last month (a date given as a period means its end).

    Stage · Stage history10.09.2025. Zawieszenie wiechy na dachu nowego budynku
    FundingDofinansowanie z Ministerstwa Zdrowia wynosi 802 098 000 zł
  2. Rynek ZdrowiaSep 2023
    Original dateInvestor
    Original dateZgodnie z założeniami inwestycja zostanie zrealizowana w formule "zaprojektuj i wybuduj" i oddana do użytku w pierwszej połowie 2026 roku.
    InvestorPomorski Uniwersytet Medyczny w Szczecinie poinformował o podpisaniu umowy na budowę obiektu dla przełomowej inwestycji kliniczno-dydaktyczno-badawczej.
  3. investmap.pl2023
    Current date
    Current dateOddanie centrum do użytku uczelni nastąpi w pierwszej połowie 2026 r.
    Locationprzy ul. Unii Lubelskiej w Szczecinie naprzeciw szpitala klinicznego SPSK-1 PUM
  4. Pomorski Uniwersytet Medyczny w Szczecinie