Programme for the Oder 2006 (multi-year programme for the modernisation of the Oder Water System)

supersededstage: constructiondelayedrestructured
PLN 9.0 billion
programme budget (multi-year) · 2001 pricesnet or gross: not recorded≈ PLN 9.0 billion (value-by-stage, est., nominal)planned funding: state funds, state special fund, other sourcesLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Programme for the Oder 2006 was a multi-year government programme for the modernisation of the Oder Water System, established by the Act of 6 July 2001 on the establishment of the multi-year programme “Programme for the Oder – 2006” (Journal of Laws 2001 No. 98 item 1067). The programme covered eight voivodeships in the Oder river basin and was to be implemented between 2002 and 2016, coordinated by the Government Plenipotentiary for the Programme for the Oder – 2006, a role held by the Voivode of Lower Silesia. Its scope covered the construction of passive and active flood-protection systems, protection of the environment and water quality, removal of flood damage, river regulation works and embankments, ecosystem renaturalisation, increasing forest cover, and the maintenance and development of inland shipping. The Act capped total spending on the Programme at PLN 9,048,960,386 (including PLN 5,561,591,582 from the state budget), fixed at 2001 task prices. As at the end of 2013, implementation of the programme (including tasks already completed) totalled PLN 5,327 million. The Supreme Audit Office (NIK) assessed the implementation of the programme negatively, pointing to major delays. In connection with European Commission requirements for a uniform approach to water management and flood protection, the act establishing the programme was repealed, and from 1 January 2015 the tasks of the abolished programme were taken over by the President of the National Water Management Authority (Krajowy Zarząd Gospodarki Wodnej); some flood-protection tasks were subsequently continued under the Oder-Vistula Flood Protection Project (POPDOW).

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverypartial[5]
Scheduledelayed[5]
Scopesuperseded[3]

Timeline

  1. Announced6 Jul 2001
  2. Construction start2002
  3. Original date2016

Change history

  • 1 Jan 2015status: supersededUstawę ustanawiającą program uchylono ustawą z dnia 28 listopada 2014 r. (Dz.U. 2014 poz. 1856); od 1 stycznia 2015 r. zadania zniesionego programu przejął Prezes Krajowego Zarządu Gospodarki Wodnej, a ochronę przeciwpowodziową w dorzeczu Odry kontynuowano m.in. w ramach Projektu Ochrony Przeciwpowodziowej w Dorzeczu Odry i Wisły (POPDOW).
  • 2002status: in progressRozpoczęcie realizacji programu wieloletniego ustanowionego ustawą z 6 lipca 2001 r.; program miał być realizowany w latach 2002–2016.

Significance

Programme for the Oder 2006 was one of the largest post-war water management programmes in the Oder river basin, covering eight voivodeships and envisaging spending of up to approximately PLN 9 billion (at 2001 prices). It included the construction of weirs, polders and flood-retention reservoirs as well as river regulation works and embankments, but some key investments were not completed during the period the programme was in force. The programme was abolished before its objectives were fully achieved, and its flood-protection functions for the Oder were taken over by instruments of unified water management, including the Oder-Vistula Flood Protection Project (POPDOW).

Sources 10 · 8 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. ISAP / eli.gov.pl (Dziennik Ustaw)6 Jul 2001
  2. Prawo.pl2014
    Scopeobejmował on osiem województw
  3. PortalSamorzadowy.pl2014
    StatusCostScope
    Status · Scopeod dnia 1 stycznia 2015 r. (tj. od dnia wejścia w życie ustawy) zadania zniesionego programu będą realizowane przez prezesa Krajowego Zarządu Gospodarki
    Cost„Program dla Odry – 2006”, wg stanu na koniec 2013 r.,(w tym zadania już zakończone) zamyka się kwotą 5 mld 327 mln zł
  4. Regionalna Dyrekcja Lasów Państwowych we Wrocławiu
    Investor
    InvestorW myśl rozporządzenia Pełnomocnikiem jest Wojewoda Dolnośląski.
  5. BANK.pl
    ScheduleDelivery
    Schedulerealizacja programu odbywa się z dużymi opóźnieniami
    DeliveryNa rok 2010 w jego ramach zaplanowano zakończenie 13 zadań. Udało się doprowadzić do finału jedynie 6.
  6. Wikipedia (pl)
    Announced
    AnnouncedProgram dla Odry 2006 – wieloletni program modernizacji Odrzańskiego Systemu Wodnego, przyjęty ustawą z dnia 6 lipca 2001 r. o ustanowieniu programu wieloletniego „Program dla Odry – 2006"
  7. Najwyższa Izba Kontroli
  8. ISAP - Internetowy System Aktów Prawnych28 Nov 2014
  9. StageCostConstruction startOriginal dateFunding
    Stage · Construction start · Original dateProgram jest programem wieloletnim w rozumieniu art. 80 ustawy z dnia 26 listopada 1998 r. o finansach publicznych (Dz. U. Nr 155, poz. 1014, z 1999 r. Nr 38, poz. 360, Nr 49, poz. 485, Nr 70, poz. 778 i Nr 110, poz. 1255, z 2000 r. Nr 6, poz. 69, Nr 12, poz. 136, Nr 48, poz. 550, Nr 95, poz. 1041, Nr 119, poz. 1251 i Nr 122, poz. 1315 oraz z 2001 r. Nr 45, poz. 497, Nr 46, poz. 499 i Nr 88, poz. 961) i jest realizowany w latach 2002-2016.
    Cost · FundingŁączne nakłady na finansowanie Programu w całym okresie jego realizacji nie mogą przekroczyć kwoty 9.048.960.386 zł, w tym 5.561.591.582 zł z budżetu państwa, ustalonej w cenach zadań z roku 2001 i przeliczanej na ceny z roku realizacji zadań.
    Costustalonej w cenach zadań z roku 2001
    Funding2 NFOŚiGW oraz WFOŚiGW *) 1.914.440.851
    Funding5 Inne (gminy, prywatne) 1.572.927.952
  10. Najwyższa Izba Kontroli20 Feb 2012P/10/180/LWR