Narew Programme – Short-Range Air Defence (CAMM-ER)

under constructionstage: construction
PLN 930 million
programme budget (multi-year) · data from 2025net or gross: not recorded≈ PLN 930 million (value-by-stage, est., nominal)funding: state special fundLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A programme to acquire short-range ground-based air defence for the Polish Armed Forces, based on CAMM-ER missiles and iLauncher launchers. In September 2023, the Armament Agency awarded the PGZ-NAREW Consortium an order with a total value of approx. PLN 54 billion gross for the delivery of key elements of 23 batteries (over 1,000 CAMM-ER missiles and 138 iLauncher launchers), with deliveries in the years 2027–2035. In November 2023, Polska Grupa Zbrojeniowa S.A., as leader of the consortium, concluded a contract with MBDA UK Ltd worth over GBP 4 billion (over PLN 20 billion) for the delivery of missile and launcher components and a transfer of technology enabling their production and assembly in Poland. The record values of the entire programme (PLN 54 billion) and of the MBDA contract (over PLN 20 billion) largely comprise purchases from a foreign entity and are not a domestic production outlay. The cost field includes exclusively the separated Polish outlay on launching production: the 2025 recapitalisation of the PGZ NAREW companies with PLN 930.17 million from the Capital Investment Fund, allocated among others to the production capacity for the rocket engine and warhead at Mesko, the CAMM-ER production hall at the Military Electronic Works (Wojskowe Zakłady Elektroniczne), and the construction of the Armament and Systems Integration Centre at OBR CTM. This amount is a 2025 tranche, and not the total target production outlay.

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Construction start2023
  2. Original date2035
  3. Current date2035

Change history

  • 30 Dec 2025stage: construction
  • 5 Sep 2023stage: announced

Significance

Narew is a flagship pillar of the Polonisation of short-range air defence and the second element – alongside the medium-range Wisła – of a multi-layered anti-aircraft shield. The launch in the country of the production and assembly of CAMM-ER missiles and iLauncher launchers, together with the transfer of technology from MBDA UK, is intended to build domestic production and servicing capabilities and to reduce dependence on foreign supplies. The scale of the programme (23 batteries, over 1,000 missiles, 138 launchers, deliveries through 2035) makes it one of the largest undertakings in the modernisation of the Polish Armed Forces.

Sources 6 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. DziennikZbrojny.pl8 Nov 2023
    StatusStage historyOriginal dateCurrent dateDescription
    Status · Original date · Current dateUmowy przewidują realizację dostaw w latach 2027-2035
    Stage historyZawarta wczoraj umowa podwykonawcza jest zgodna z zakresem dwóch umów podpisanych 5 września 2023 roku pomiędzy Agencją Uzbrojenia a Konsorcjum PGZ-NAREW, obejmuje zatem dostawę wyrzutni i rakiet CAMM-ER dla 23 baterii systemu Narew oraz nie zmienia planowanego okresu dostaw przypadającego na lata 2027-2035.
    Descriptionponad 1000 pocisków rakietowych CAMM-ER i dostosowanych do ich użycia 138 wyrzutni rakiet iLauncher dla 23 baterii
    Namenaziemnej obrony powietrznej krótkiego zasięgu kr. Narew
  2. ZBiAM8 Nov 2023
    Construction startInvestorDescription
    Construction start · InvestorPolska Grupa Zbrojeniowa S.A., jako lider Konsorcjum PGZ-NAREW w skład którego wchodzą także: Huta Stalowa Wola S.A., Jelcz Sp. z o.o., MESKO S.A., Ośrodek Badawczo-Rozwojowy Centrum Techniki Morskiej S.A., PCO S.A., PIT-RADWAR S.A., Wojskowe Zakłady Łączności Nr 1 S.A., Wojskowe Zakłady Uzbrojenia S.A., Wojskowe Zakłady Elektroniczne S.A. i Zakłady Mechaniczne Tarnów S.A., zawarła umowę z firmą MBDA UK Ltd
    Descriptionwartość przekracza 4 mld GBP (ponad 20 mld PLN)
  3. Defence2430 Dec 2025
    StageStage historyCost
    Stagejeśli chodzi o OBR CTM celem jest budowa Centrum Integracji Uzbrojenia i Systemów.
    Stage historyw Wojskowych Zakładach Elektronicznych oCAMM-ER wraz z halą produkcyjną
    CostBędą one finansowane z Funduszu Inwestycji Kapitałowych, a łączna wartość dokapitalizowania spółek wchodzących w skład PGZ NAREW w 2025 roku wyniesie 930,17 miliona złotych.
  4. WNP.pl
  5. Ministerstwo Obrony Narodowej (gov.pl)
  6. Funding
    FundingBędą one finansowane z Funduszu Inwestycji Kapitałowych, a łączna wartość dokapitalizowania spółek wchodzących w skład konsorcjum PGZ NAREW wyniesie 930,17 miliona złotych.
    FundingUchwałą nr 68 Rady Ministrów z 25-go czerwca 2024 roku w sprawie dokapitalizowania spółek wchodzących w skład Konsorcjum PGZ-NAREW, na inwestycje w spółkach PGZ przyznano środki w wysokości ok. 3 888,11 mln PLN