Enea Group battery energy storage programme (approx. 1.4 GW)

plannedstage: tender
PLN 2.0 billion
estimate · data from Mar 2026net or gross: not recorded≈ PLN 2.0 billion (value-by-stage, est., nominal)funding: National Recovery Plan, EU fundsThe amount covers the whole investment programme: 1,386 MW of energy storage plus about 300 MW of photovoltaic projects.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Enea Group's battery energy storage programme, with a combined power of 1,386 MW and more than 3,000 MWh of capacity, announced in March 2026 together with about 300 MW of photovoltaic projects. It comprises 11 standalone high-voltage storage units (580 MW), 24 medium-voltage units (242 MW), 16 hybrid units at photovoltaic farms (124 MW), an 8 MW grid storage unit and two large-scale facilities at the Kozienice (232 MW) and Połaniec (200 MW) power plants. Enea estimated the cost of the whole programme, including the photovoltaic part, at about PLN 2 billion. For battery storage alone, the company plans to spend nearly PLN 1.4 billion over the next two years. Construction of 11 photovoltaic farms with about 268 MW is financed by a Recovery and Resilience Facility (KPO) loan from BGK of more than PLN 417 million, and the grid storage unit in Debrzno-Wieś received PLN 22 million from the Modernisation Fund. In May 2026 bids were opened in a tender for the supply of components with up to 840 MWh of capacity. In September 2026 the company said the Kozienice and Połaniec projects had received corporate approvals and that selection of contractors and technology suppliers was under way. Under the schedule in the presentation of the 2025 results, 866 MW is to be built in 2027, about 80 MW in 2028 and 432 MW in 2029.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. AnnouncedMar 2026
  2. Original date2029
  3. Current date2029

Change history

  • Mar 2026stage: announced
  • Mar 2026stage: tender

Significance

Once completed, the programme is to give the Enea Group about 1.4 GW of battery storage power, more than the target of over 1.3 GW set in the group's strategy to 2035. The company plans to use the storage to shift energy sales from cheap midday hours to more expensive evening hours. The hybrid units are to reshape the output profile of the group's photovoltaic farms.

Sources 6 · 5 independent · 2 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Parkiet12 Mar 2026
    CostOriginal dateInvestor
    CostCały program inwestycyjny, jak mówił wiceprezes ds. handlowych Bartosz Krysta, jest przewidziany do realizacji w 30 miesięcy. Instalacje będą oddawane etapami, a ostatnie będą podłączane do sieci w 2029 r. Koszt tego programu oszacowano na 2 mld zł.
    Original dateInstalacje będą oddawane etapami, a ostatnie będą podłączane do sieci w 2029 r.
    InvestorGrupa Enea planuje budowę magazynów energii o łącznej mocy 1386 MW i projektów fotowoltaicznych o mocy ok. 300 MW.
    LocationCo ważne, Enea wybuduje także duże wielkoskalowe magazyny energii przy swoich centrach energetycznych, którymi są Kozienice i Połaniec. W pierwszej lokalizacji powstanie magazyn o mocy 232 MW, a w drugiej o mocy 200 MW.
  2. WysokieNapiecie.pl11 Mar 2026
    Announced
    AnnouncedGrupa Enea planuje realizację magazynów energii o łącznej mocy 1386 MW i projektów fotowoltaicznych o mocy ok. 300 MW w ciągu maksymalnie 30 miesięcy, poinformował wiceprezes ds. handlowych Bartosz Krysta. Wartość tego programu inwestycyjnego to ok. 2 mld zł.
  3. Gramwzielone.pl11 May 2026
    StageCurrent date
    StageObecnie prowadzone jest postępowanie mające na celu wyłonienie dostawców sporej części z tych inwestycji.
    Current dateAktualny plan Enei zakłada, że magazyny energii o mocy 866 MW będą gotowe w 2027 r., w 2028 r. planowane jest przyłączenie mniejszego wolumenu rzędu 80 MW, a w 2029 r. moce magazynów energii w portfelu grupy energetycznej mają wzrosnąć o kolejne 432 MW.
  4. Enea15 Sep 2026
    StatusFunding
    StatusKontynuowane są przygotowania do budowy wielkoskalowych magazynów energii o mocy około 200 MW na terenach Enei Wytwarzanie i Enei Elektrowni Połaniec. Projekty uzyskały wymagane zgody korporacyjne, a Grupa prowadzi proces wyboru wykonawców i dostawców technologii.
    FundingZarządzająca aktywami OZE w Grupie, spółka Enea Nowa Energia zawarła z Bankiem Gospodarstwa Krajowego umowę pożyczki finansowanej ze środków Krajowego Planu Odbudowy o wartości ponad 417 mln zł. Finansowanie zostanie przeznaczone na budowę i rozwój 11 projektów fotowoltaicznych o łącznej mocy około 268 MW.
  5. Gramwzielone.pl23 Apr 2026
    Funding
    FundingPrzed rokiem Enea Operator – spółka dystrybucyjna z grupy Enea – otrzymała 22 mln zł dofinansowania z unijnego Funduszu Modernizacji na budowę magazynu energii o mocy 8 MW i pojemności 8 MWh w miejscowości Debrzno-Wieś w powiecie złotowskim.
  6. StockWatch.pl11 Mar 2026