Homar-K Programme – Rocket Artillery (K239 Chunmoo, CGR-080 production in Poland)

operating, being expandedstage: operational
funding: state special fund, foreign loan

The Homar-K programme is the acquisition for the Polish Armed Forces of South Korean K239 Chunmoo multiple-launch rocket systems (in the Polish version on a Jelcz chassis and with the Topaz fire-control and command system from WB Group). The framework agreement of 19 October 2022 provides for the delivery of a total of 288 launchers for 16 rocket artillery battalions in the years 2023–2028, together with a stock of ammunition. The first executive contract (USD 3.55 billion net) was concluded on 4 November 2022, and the first launchers reached units (including the 18th Artillery Regiment) as early as 2023. A second executive contract worth approx. USD 1.6 billion net for 72 launcher modules, with delivery in 2026–2029, was concluded in April 2025. In December 2025, the Armament Agency concluded an executive contract worth approx. PLN 14 billion for the delivery of thousands of Polish-made CGR-080 guided missiles (calibre 239 mm, range up to 80 km); these will be manufactured by the joint-venture company Hanwha WB Advanced Systems (Hanwha Aerospace and WB Group) in a new plant in Gorzów Wielkopolski. Because the programme is dominated by the purchase of armament in South Korea, the record serves a strategic visibility function, and the recorded amount covers only the isolable Polish component of CGR-080 missile production, not the full value of the programme (on the order of tens of billions of PLN). The record is purely strategic in character (visibility of the defence programme), and its cost is not counted toward the 'value by stage' aggregate, because the amounts quoted are the value of armament-acquisition contracts, not a separated outlay on Polish production.

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Announced19 Oct 2022
  2. Original date2028
  3. Current date2029

Change history

  • 2023stage: operational
  • 19 Oct 2022stage: announced

Significance

Homar-K is building the backbone of Poland's long-range rocket artillery, multiplying many times over the number and range of launchers (the CGR-080 missile reaches up to 80 km) compared with worn-out Soviet-generation systems. A key element of the programme is – for the first time in history – the launch in Poland of the production of precision ammunition for rocket artillery: the CGR-080 missiles are to be produced at the plant of the joint-venture company Hanwha WB Advanced Systems in Gorzów Wielkopolski, together with a transfer of technology to WB Group. Domestic missile production reduces dependence on foreign supplies and creates durable industrial and servicing capabilities in the area of rocket ammunition.

Sources 7 · 5 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. DziennikZbrojny.plApr 2025
    StatusStageStage historyAnnouncedOriginal dateCurrent dateInvestor
    StatusPrzedmiotem umowy o wartości ok. 1,6 mld USD netto (ok. 7,87 mld PLN brutto), zawartej pomiędzy Agencją Uzbrojenia a południowokoreańską spółką Hanwha Aerospace Co. Ltd., jest dostawa 72 modułów wyrzutni w latach 2026-2029
    Stagepozostałe 15 egzemplarzy w 2023 roku przekazano do 18. Pułku Artylerii
    Stage history · Announced · Original dateZawarty dziś kontrakt jest konsekwencją umowy ramowej z 19 października 2022 roku przewidującej dostawy łącznie 288 wyrzutni (dla 16 dywizjonów artylerii rakietowej) w latach 2023-2028 wraz z zapasem amunicji
    Current datejest dostawa 72 modułów wyrzutni w latach 2026-2029
    Investorzawartej pomiędzy Agencją Uzbrojenia a południowokoreańską spółką Hanwha Aerospace Co. Ltd.
  2. Defence24Dec 2025
    Significance
    SignificancePo pierwsze, ma dotyczyć produkcji w Polsce, po raz pierwszy w historii, precyzyjnej amunicji do artylerii rakietowej.
  3. Portal ObronnyDec 2025
    Description
    LocationW Gorzowie Wielkopolskim rozpoczęły się prace przygotowawcze do budowy nowoczesnego zakładu produkcyjnego
    Descriptionfabryka będzie odpowiedzialna za wytwarzanie precyzyjnych pocisków rakietowych CGR-080 dla systemów artylerii HOMAR-K
  4. MILMAGDec 2025
  5. Defence24Nov 2025
  6. Funding
    Fundingzawarciu umów na finansowanie zamówień na dostawy czołgów K2/K2PL oraz pocisków rakietowych CGR-080 dla systemu Homar-K, które będą finansowane ze środków FWSZ.
  7. Funding
    FundingPolskie zakupy zbrojeniowe w Korei realizowane są na podstawie kredytu udzielonego przez bank eksportowy Korei – Eximbank.