Port Czystej Energii (waste-to-energy plant, ITPOK) in Gdańsk-Szadółki
A municipal waste thermal treatment installation in Szadółki, Gdańsk, built and operated under a public-private partnership formula. The plant, with a capacity of approximately 160 thousand tonnes of waste per year, incinerates the residual fraction (unsuitable for recycling) from Gdańsk and several dozen surrounding municipalities, producing electricity and district heating. The official opening took place on 24 March 2025. The owner of the installation is the municipal company Port Czystej Energii sp. z o.o., while the private partner responsible for the design, construction and 25-year operation is an Italian-French consortium (Webuild/Astaldi, Termomeccanica Ecologia, TIRU Paprec Energies).
How it went
This record carries no outcome assessment on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
Timeline
- Announced7 May 2018
- Construction start18 Dec 2020
- Delivery24 Mar 2025
Change history
- 24 Mar 2025status: completedCeremonial opening of the Port Czystej Energii installation.
- 24 Mar 2025stage: operational
- 18 Dec 2020stage: construction
Significance
The plant completes Gdańsk's waste management system, providing final thermal disposal of the non-recyclable waste fraction instead of landfilling it. It is to process approximately 160 thousand tonnes of waste per year, generating approximately 114,000 MWh of electricity and 509,000 GJ of district heating – enough to heat approximately 19 thousand households in winter, and up to 70 thousand in summer. The installation replaces fossil fuels with waste as fuel and is in line with the policy of reducing the landfilling of municipal waste.
Sources 5 · 4 independent · 5 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Ministerstwo Klimatu i Środowiska (gov.pl)24 Mar 2025StatusCostDelivery
Status · Delivery24 marca 2025 r. oficjalnie otwarto Port Czystej Energii
CostŁączny koszt inwestycji wyniósł ponad 661 mln zł netto (813,6 mln zł brutto).
- Wikipedia (pl)2025Construction start
Construction startRozpoczęcie budowy 18 grudnia 2020
Location54°19′20,5″N 18°32′25,0″E/54,322361 18,540278
- Urząd Miejski w Gdańsku (gdansk.pl)AnnouncedInvestor
Announced7 maja 2018 r. podpisano umowę z włosko-francuskim konsorcjum Astaldi (WeBuild), Termomeccanica Ecologia oraz TIRU
InvestorSpółka PCE jako miejski inwestor nadzoruje proces budowy, a w dalszej kolejności czuwać będzie nad prawidłowością procesu eksploatacji zakładu
- [4]Pół roku i 50 tys. ton przekształconych termicznie odpadów. Tak działa Port Czystej Energii ↗archived ✓Pomorskie.eu (Urząd Marszałkowski Woj. Pomorskiego)2025Stage
StageW ciągu pół roku działalności PCE przyjęło niemal 50 tys. ton odpadów.
- Funding
FundingDofinansowanie w wysokości 271 mln zł pochodziło z Programu Operacyjnego Infrastruktura i Środowisko 2014-2020.
FundingKolejne 330 mln zł zapewnił Narodowy Fundusz Ochrony Środowiska i Gospodarki Wodnej
Fundingresztę pokryły kredyty komercyjne.