Port Czystej Energii (waste-to-energy plant, ITPOK) in Gdańsk-Szadółki

completedstage: operational
661 mln PLN
programme budget (multi-year) · data from Mar 2025net of VAT≈ 661 mln PLN (value-by-stage, est., nominal)funding: EU Cohesion Fund (approx. PLN 271 million), NFOŚiGW (approx. PLN 330 million), commercial loans

A municipal waste thermal treatment installation in Szadółki, Gdańsk, built and operated under a public-private partnership formula. The plant, with a capacity of approximately 160 thousand tonnes of waste per year, incinerates the residual fraction (unsuitable for recycling) from Gdańsk and several dozen surrounding municipalities, producing electricity and district heating. The official opening took place on 24 March 2025. The owner of the installation is the municipal company Port Czystej Energii sp. z o.o., while the private partner responsible for the design, construction and 25-year operation is an Italian-French consortium (Webuild/Astaldi, Termomeccanica Ecologia, TIRU Paprec Energies).

How it went

This record carries no outcome assessment on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Announced7 May 2018
  2. Construction start18 Dec 2020
  3. Delivery24 Mar 2025

Change history

  • 24 Mar 2025status: completedCeremonial opening of the Port Czystej Energii installation.
  • 24 Mar 2025stage: operational
  • 18 Dec 2020stage: construction

Significance

The plant completes Gdańsk's waste management system, providing final thermal disposal of the non-recyclable waste fraction instead of landfilling it. It is to process approximately 160 thousand tonnes of waste per year, generating approximately 114,000 MWh of electricity and 509,000 GJ of district heating – enough to heat approximately 19 thousand households in winter, and up to 70 thousand in summer. The installation replaces fossil fuels with waste as fuel and is in line with the policy of reducing the landfilling of municipal waste.

Sources 5 · 4 independent · 5 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Klimatu i Środowiska (gov.pl)24 Mar 2025
    StatusCostDelivery
    Status · Delivery24 marca 2025 r. oficjalnie otwarto Port Czystej Energii
    CostŁączny koszt inwestycji wyniósł ponad 661 mln zł netto (813,6 mln zł brutto).
  2. Wikipedia (pl)2025
    Construction start
    Construction startRozpoczęcie budowy 18 grudnia 2020
    Location54°19′20,5″N 18°32′25,0″E/54,322361 18,540278
  3. Urząd Miejski w Gdańsku (gdansk.pl)
    AnnouncedInvestor
    Announced7 maja 2018 r. podpisano umowę z włosko-francuskim konsorcjum Astaldi (WeBuild), Termomeccanica Ecologia oraz TIRU
    InvestorSpółka PCE jako miejski inwestor nadzoruje proces budowy, a w dalszej kolejności czuwać będzie nad prawidłowością procesu eksploatacji zakładu
  4. Pomorskie.eu (Urząd Marszałkowski Woj. Pomorskiego)2025
    Stage
    StageW ciągu pół roku działalności PCE przyjęło niemal 50 tys. ton odpadów.
  5. Funding
    FundingDofinansowanie w wysokości 271 mln zł pochodziło z Programu Operacyjnego Infrastruktura i Środowisko 2014-2020.
    FundingKolejne 330 mln zł zapewnił Narodowy Fundusz Ochrony Środowiska i Gospodarki Wodnej
    Fundingresztę pokryły kredyty komercyjne.