Port Czystej Energii (waste-to-energy plant, ITPOK) in Gdańsk-Szadółki
A municipal waste thermal treatment installation in Szadółki, Gdańsk, built and operated under a public-private partnership formula. The plant, with a capacity of approximately 160 thousand tonnes of waste per year, incinerates the residual fraction (unsuitable for recycling) from Gdańsk and several dozen surrounding municipalities, producing electricity and district heating. The official opening took place on 24 March 2025. The owner of the installation is the municipal company Port Czystej Energii sp. z o.o., while the private partner responsible for the design, construction and 25-year operation is an Italian-French consortium (Webuild/Astaldi, Termomeccanica Ecologia, TIRU Paprec Energies).
Timeline
- Announced 7 May 2018
- Construction start 18 Dec 2020
- Delivery 24 Mar 2025
Change history
- 24 Mar 2025 status: completed Ceremonial opening of the Port Czystej Energii installation.
- 24 Mar 2025 stage: operational
- 18 Dec 2020 stage: construction
Significance
The plant completes Gdańsk's waste management system, providing final thermal disposal of the non-recyclable waste fraction instead of landfilling it. It is to process approximately 160 thousand tonnes of waste per year, generating approximately 114,000 MWh of electricity and 509,000 GJ of district heating — enough to heat approximately 19 thousand households in winter, and up to 70 thousand in summer. The installation replaces fossil fuels with waste as fuel and is in line with the policy of reducing the landfilling of municipal waste.
Sources 4
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Ministerstwo Klimatu i Środowiska (gov.pl) 24 Mar 2025StatusStageCostDeliveryDescriptionSignificance
Status „24 marca 2025 r. oficjalnie otwarto Port Czystej Energii"
Cost „Łączny koszt inwestycji wyniósł ponad 661 mln zł netto (813,6 mln zł brutto)."
- Wikipedia (pl) 2025Construction startInvestorSignificance
Construction start „18 grudnia 2020"
locations „54°19′20,5″N 18°32′25,0″E/54,322361 18,540278"
- Urząd Miejski w Gdańsku (gdansk.pl)InvestorAnnouncedDescriptionSignificance
Announced „7 maja 2018 r. podpisano umowę z włosko-francuskim konsorcjum Astaldi (WeBuild), Termomeccanica Ecologia oraz TIRU"
Investor „Spółka PCE jako miejski inwestor nadzoruje proces budowy, a w dalszej kolejności czuwać będzie nad prawidłowością procesu eksploatacji zakładu"
- Pomorskie.eu (Urząd Marszałkowski Woj. Pomorskiego) 2025Stage
Stage „W ciągu pół roku działalności PCE przyjęło niemal 50 tys. ton odpadów."