🛡Defencestrategic

Polonization of K2PL tank production at ZM Bumar-Łabędy (Gliwice)

under constructionstage: construction
PLN 850 million
programme budget (multi-year) · data from Oct 2025net or gross: not recorded≈ PLN 850 million (value-by-stage, est., nominal)funding: state special fundLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A programme to rebuild Poland's capacity to produce tanks based on a Polonized version of the Korean K2 tank – the K2PL. Under the Armament Agency's contract with Hyundai Rotem worth approximately USD 6.5 billion, the final assembly of 61 of the 64 ordered tanks in the K2PL version is to be carried out at Zakłady Mechaniczne "Bumar-Łabędy" in Gliwice, a company of the Polska Grupa Zbrojeniowa. The Gliwice plant was designated as the main location following a site survey conducted by Hyundai Rotem, which assessed, among others, Wojskowe Zakłady Motoryzacyjne in Poznań and OBRUM; ZM Bumar-Łabędy received the highest rating for production capabilities. To prepare the infrastructure for the project, PGZ is recapitalizing the company with PLN 850 million from the Capital Investment Fund. In October 2025, an agreement was signed regulating the technology transfer, the construction of the assembly line, and the servicing of tanks in the country. The first K2PL tank made in Poland is to be built in 2028 and delivered to the army in 2029, while deliveries of units in the K2PL configuration are planned for 2028–2030. The supply chain includes several dozen Polish companies.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. AnnouncedOct 2025
  2. Original date2030
  3. Current date2030

Change history

  • Oct 2025stage: announced
  • Oct 2025stage: construction

Significance

The return of serial tank production to Poland after nearly two decades and the rebuilding of domestic capacity to produce modern armoured vehicles at the Bumar-Łabędy plant in Gliwice. Launching the K2PL assembly line together with the transfer of technology, documentation and servicing processes from Hyundai Rotem strengthens Poland's defence potential and makes the maintenance of the tank fleet independent of foreign centres. The project secures and develops the industrial base and workforce competencies (experience in producing the T-72 and PT-91) in the Śląskie Voivodeship and engages a broad supply chain of Polish defence companies.

Sources 6 · 4 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Polska Zbrojna
    Original dateCurrent date
    Location61 powstanie w gliwickich zakładach „Bumar-Łabędy”
    Original date · Current dateich dostawy przewidziano na lata 2028–2030
  2. Portal Obronny
  3. Nowiny Gliwice31 Oct 2025
    AnnouncedStage history
    Announced · Stage historyWe wtorek w siedzibie Polskiej Grupy Zbrojeniowej podpisana została umowa
  4. ZBiAM6 Oct 2025
    StatusStageInvestorCostStage historyFunding
    Statuswdrażana inwestycja pozwoli nie tylko znacząco zwiększyć nasze zdolności produkcyjne, ale przede wszystkim wzmocni potencjał obronny Polski
    Stage · Stage historyprzywrócenie w gliwickim zakładzie zdolności do produkcji nowoczesnych pojazdów opancerzonych
    Investor · Costprzekaże Zakładom Mechanicznym „Bumar-Łabędy” S.A. środki z Funduszu Inwestycji Kapitałowych o wartości 850 mln PLN
    FundingNa mocy umowy Polska Grupa Zbrojeniowa S.A. przekaże Zakładom Mechanicznym „Bumar-Łabędy” S.A. środki z Funduszu Inwestycji Kapitałowych o wartości 850 mln PLN.