← all projects
🌊Environmentstrategic

Racibórz Dolny flood-control reservoir

completedstage: operationaldelivereddelayedover budget
2.0 bn PLN
programme budget (multi-year) · data from 2020net or gross: not recorded≈ 2.0 bn PLN (value-by-stage, est., nominal)funding: EU – POIiŚ 2014-2020: PLN 667.04 million in funding, World Bank loan: PLN 283.6 million, state budget and other national funds

A dry flood-control reservoir (polder) on the Oder in the Śląskie Voivodeship, on the lands of Racibórz and the communes of Krzyżanowice, Kornowac, Lubomia, and Gorzyce – the largest flood-control structure in Poland, with a capacity of 185 million m³ at maximum damming and an area of 2,626 ha. The construction contract was concluded on 18 June 2013 with the Spanish company Dragados, with an original completion date of January 2017; in the autumn of 2016 the contractor withdrew from the contract at approx. 43 percent progress of the works. Completion was entrusted on 30 November 2017 to the Budimex-Ferrovial Agroman consortium (contract of approx. PLN 903 million, finalisation planned by 2019). The reservoir was officially put into service on 30 June 2020. The project's value amounted to approx. PLN 1.995 billion, including PLN 667 million of EU funding from the Operational Programme Infrastructure and Environment 2014–2020 and a World Bank loan.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. How to read this section

Deliverydelivered[1]
Scheduledelayed[1]
Budgetover budget[3]
Utilisationin use[4]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

water captured in flood-storage mode during the flood of September 2024 vs total reservoir capacity
147/185mn m3(2024-09)79% utilisation

Timeline

Slip: +41 mo. vs. the original date

  1. Announced2001
  2. Construction start18 Jun 2013
  3. Original dateJan 2017
  4. Last stated date2019
  5. Delivery30 Jun 2020

Change history

  • 30 Jun 2020stage: operational
  • 18 Jun 2013stage: construction

Significance

The reservoir provides flood protection to approx. 2.5 million residents of three Oder-side voivodeships (Śląskie, Opolskie, and Dolnośląskie) and is capable of reducing flood waves comparable to the catastrophic wave of 1997. During the flood in September 2024 the structure operated in flood-damming mode from 15 to 29 September, capturing at its peak 147 million m³ of water (approx. 80% of capacity) and flattening the flood wave on the Oder – the first such large test in its history.

Sources 7 · 5 independent · 7 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusAnnouncedOriginal dateDeliveryStage historySchedule
    Status · Delivery · Stage history · Scheduleoficjalne oddanie do użytku nastąpiło 30 czerwca 2020 roku
    AnnouncedW 2001 roku przyjęty został Program dla Odry 2006
    Original datePierwotnie zakończenie budowy planowano na styczeń 2017 roku
    Location50°02′16″N 18°15′23″E
  2. PGW Wody Polskie – RZGW w Gliwicach (gov.pl)
    StageFundingDescriptionSignificanceUtilisation
    Stage01.2020r. – Zbiornik osiąga swoją funkcjonalność
    Funding283,6 mln PLN
    Locationwojewództwa śląskiego, na terenach należących do miasta Raciborza oraz gmin Krzyżanowice, Kornowac, Lubomia i Gorzyce
    Description · Utilisationobjętość wody przy maksymalnym piętrzeniu – 185,0mln m3
    DescriptionObiekt ten zajmie powierzchnię 2626 ha, na której znajdować będzie się czasza zbiornika, obwałowania, kanał zrzutowy oraz obiekty melioracyjne regulujące stosunki wodne na przyległym terenie.
    Significanceblisko 2,5 mln mieszkańców trzech nadodrzańskich województw
    Fundingpożyczka Międzynarodowego Banku Odbudowy i Rozwoju (Bank Światowy) (umowa pożyczki zawarta pomiędzy Rządem RP, a Bankiem z 11.05.2007 roku) - kwota dofinansowania wynosi 283,6 mln PLN
    Fundingkredyt Banku Rozwoju Rady Europy (umowa kredytu zawarta pomiędzy Rządem RP, a Bankiem z 11.05.2007 roku) - kwota dofinansowania wynosi 489,84 mln PLN
    Fundingśrodki towarzyszące Budżetu Państwa - kwota dofinansowania wynosi 117,2 mln PLN
    Fundingśrodki Narodowego Funduszu Ochrony Środowiska i Gospodarki Wodnej - kwota dofinansowania wynosi 41,6 mln PLN
  3. Konkret24 / TVN2416 Sep 2024
    Construction startStage historyDescriptionBudget
    Construction start · Stage historyUmowę na budowę zbiornika Racibórz Dolny zawarto 18 czerwca 2013 roku
    DescriptionRegionalny Zarząd Gospodarki Wodnej w Gliwicach powiadomił o odstąpieniu od umowy
    BudgetPierwotnie firma miała wykonać prace w 48 miesięcy, czyli do 2017 roku, za 936 mln zł.
    BudgetKoszt inwestycji dofinansowanej ze środków Unii Europejskiej, Banku Światowego, Banku Rozwoju Rady Europy oraz budżetu państwa wyniósł ok. 2 mld zł.
  4. PGW Wody Polskie – RZGW w Gliwicach (gov.pl)29 Oct 2024
    SignificanceUtilisation
    Significance · UtilisationObiekt ten pierwszy raz w swojej wciąż krótkiej historii istnienia przechwycił tak dużą ilość wody (147 mln m3) i udowodnił jak ważna była jego rola
  5. Mapa Dotacji UE (gov.pl)
    CostFundingInvestor
    Costwartość projektu 1 995 176 677,48 zł
    Funding667 040 000,00 zł
    InvestorPAŃSTWOWE GOSPODARSTWO WODNE WODY POLSKIE - RZGW W GLIWICACH
  6. Rynek Infrastruktury30 Nov 2017
    Current date
    Current dateBudimex w konsorcjum z Ferrovial Agroman dokończy budowę zbiornika Racibórz Dolny. Inwestycja ma być sfinalizowana do 2019 roku.
  7. Budimex S.A.30 Nov 2017
    Description
    DescriptionZakres prac obejmuje budowę suchego zbiornika przeciwpowodziowego o długości 22,4 km i wysokości 11 m