Green Unit at the Połaniec Power Plant (a power unit fired 100% by biomass, 205 MW)

completedstage: operationaldelivered
PLN 1.0 billion
estimate · data from 2013net or gross: not recorded≈ PLN 1.0 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Green Unit is a 205 MW power unit fired 100 per cent by biomass (around 80 per cent wood chips and around 20 per cent agricultural residues), built at the Połaniec Power Plant in the Świętokrzyskie Voivodeship by GDF Suez Energia Polska. At the time of commissioning, it was the largest power unit fired exclusively by biomass in the world. Construction work on the fluidised-bed boiler began in November 2010; the unit was synchronised with the national grid in the autumn of 2012 and handed over for use at the end of 2012, with its official opening held on 5 June 2013. The investment was estimated at around PLN 1 billion (around EUR 240 million). The unit can supply electricity to around 600,000 households and is responsible for cutting CO2 emissions by more than 1.2 million tonnes a year compared with conventional generation. The unit's owner was initially the GDF Suez group (ENGIE); in April 2017 the Połaniec Power Plant, together with the Green Unit, became the property of the Enea group (Enea Elektrownia Połaniec S.A.).

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[4]
Utilisationin use[1]
eksploatacja bloku biomasowego
Current
blok w eksploatacji od końca 2012 r.; ok. 25% krajowej produkcji energii z biomasy w okresie uruchomienia (2013)
Capacity or target
205 MW

Timeline

  1. Construction startNov 2010
  2. Delivery2012

Change history

  • 2012stage: operational
  • Nov 2010stage: construction

Significance

At the time of commissioning, the Green Unit was the largest power unit fired 100 per cent by biomass in the world, and its output accounted for around 25 per cent of national electricity production from biomass. The investment was one of the largest single renewable-energy projects in Poland at the time, contributing to the country's commitment to generate 15 per cent of its energy from renewable sources by 2020. The 205 MW unit is able to supply around 600,000 households with electricity and cuts CO2 emissions by more than 1.2 million tonnes a year relative to conventional generation.

Sources 8 · 6 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Rynek Infrastruktury6 Jun 2013
    DeliveryStage historyUtilisation
    Delivery · Stage historyZielony Blok uruchomiony w Połańcu pod koniec 2012 r. ma moc wytwórczą 205 MW.
    UtilisationGDF Suez Energia Polska oficjalnie oddała do użytku Zielony Blok – największy na świecie blok energetyczny zasilany wyłącznie biomasą. Energia wytwarzana w kotle stanowi 25 proc. całej krajowej produkcji prądu z paliwa biomasowego.
  2. Wikipedia (pl)
  3. Forsal.pl10 Oct 2012
  4. wnp.pl2013
    StatusCostDelivery
    Status · Delivery5 czerwca br. oficjalne otwarto Zielony Blok w Elektrowni Połaniec.
    CostKoszt inwestycji to ok. 1 mld zł.
  5. Inżynieria.com2013
    StageConstruction startInvestor
    StageZielony Blok do użytku oddano pod koniec ubiegłego roku
    Construction startPrace budowlane przy konstrukcji kotła ruszyły w listopadzie 2010 r.
    InvestorJak zapewnia jego właściciel - GDF Suez