CCGT Combined-Cycle Gas-and-Steam Unit in Płock (PKN Orlen, approx. 600 MW)
A combined-cycle gas-and-steam unit (CCGT) built by PKN Orlen at its Production Plant in Płock, based on an H-class gas turbine (Siemens SGT5-8000H) in a single-shaft configuration with an SST5-5000 steam turbine. The unit has a capacity of around 596 MWe gross (also given as 600 MW) and around 520 MWt, operating in high-efficiency cogeneration, with an electrical efficiency above 61 per cent and total efficiency of around 93 per cent. PKN Orlen signed a turnkey ("pod klucz") construction contract with a consortium of Siemens AG and Siemens sp. z o.o. at the turn of November and December 2014 (tender decided: November 2014; contract announced: 2 December 2014). The value of the contracts was PLN 1.3 billion for construction and around PLN 0.3 billion for an approximately 12-year service agreement; the estimated total investment value was around PLN 1.65 billion. Construction began in September 2015, and the unit was handed over for commercial operation at the end of June 2018. Total investment outlays incurred to carry out the project came to around PLN 1.7 billion. At the time, it was the largest and most advanced combined-cycle gas-and-steam unit in Poland.
How it went
Assessment: settled, as of 29 Jun 2018. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- ok. 7 TWh prądu rocznie po oddaniu do użytku (2018)
- Capacity or target
- 596 MWe brutto / ok. 520 MWt
Timeline
- Announced2 Dec 2014
- Construction startSep 2015
- DeliveryJun 2018
Change history
- Jun 2018stage: operational
- Sep 2015stage: construction
- Nov 2014stage: tender
Significance
At the time of commissioning, the CCGT unit in Płock was the largest and most advanced combined-cycle gas-and-steam unit in Poland and one of the first units in the country to use an H-class gas turbine with an electrical efficiency above 61 per cent. It increased PKN Orlen's generating capacity in high-efficiency industrial cogeneration (alongside the unit in Włocławek), providing electricity and heat production for the needs of the Płock production plant and feeding power into the national grid. The investment was part of building Orlen's position as a leader in industrial cogeneration and of strengthening energy security based on gas fuel.
Sources 4 · 4 independent · 3 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- money.pl29 Jun 2018StageDeliveryUtilisation
Stage · UtilisationOrlen podpisał z konsorcjum firm: Siemens AG i Siemens protokół, na mocy którego zakończono realizację procesu inwestycji bloku gazowo-parowego w Płocku.
Deliveryblok gazowo-parowym w Płocku ma moc 600 MW energii elektrycznej i 520 MWt cieplnej
UtilisationPo oddaniu do użytku PKN Orlen będzie produkował ok. 7 TWh prądu, co będzie stanowiło ok 4,5 proc. polskiego rynku.
- wGospodarce.pl29 Jun 2018StatusCostDeliveryInvestorStageUtilisation
Status · Delivery · Stage · Utilisationkoncern przekazał do komercyjnej eksploatacji elektrociepłownię
CostŁączne nakłady inwestycyjne poniesione przez spółkę na realizację projektu budowy elektrowni wyniosły ok 1,7 mld zł
InvestorPKN Orlen podpisał z konsorcjum firm: Siemens AG i Siemens protokół, na mocy którego zakończono realizację procesu inwestycji bloku gazowo-parowego w Płocku - poinformowała spółka.
- Politechnika WarszawskaConstruction start
Construction startwrzesień 2015 – rozpoczęcie budowy bloku gazowo-parowego na terenie Zakładu Produkcyjnego w Płocku
- PKN Orlen S.A.2 Dec 2014Announced
Announcedkontrakt na wykonawstwo w formule „pod klucz” bloku gazowo-parowego w Płocku