464 MW Power Unit at the Pątnów II Power Plant (first supercritical-parameter unit in the National Power System)

completedstage: operationaldelivered
PLN 1.9 billion
estimate · data from 2008net or gross: not recorded≈ PLN 1.9 billion (value-by-stage, est., nominal)funding: foreign loan, state special fund, private financeThe source gives EUR 550 million. The zloty figure is our conversion at the rate for 2008, so the site fixed rate will not reproduce it.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A lignite-fired power unit with a capacity of 464 MW (the rated capacity is also given as 474 MW), built at the Pątnów Power Plant near Konin as Pątnów II. It was the first unit with supercritical parameters in the national power system. The investment was carried out by the special-purpose vehicle Elektrownia Pątnów II Sp. z o.o., a 100 per cent subsidiary of Zespół Elektrowni Pątnów-Adamów-Konin (ZE PAK) SA, set up to raise long-term credit financing; the group's strategic investor was Elektrim SA. Construction ran from 3 January 2002, and the unit was officially commissioned and handed over for operation on 29 February 2008. The boiler was supplied by the Alstom-Rafako consortium, and the turbine by Alstom Power. Construction cost was estimated at around EUR 550 million (around PLN 1.9 billion at the 2008 NBP average exchange rate). Planned annual gross electricity output was 3.3 TWh, with an efficiency of 44.0 per cent gross and 41.0 per cent net. At the end of 2020, the company Elektrownia Pątnów II was liquidated, and its assets were transferred directly to ZE PAK; the unit became Unit No. 9 of the Pątnów Power Plant.

How it went

Assessment: settled, as of 29 Feb 2008. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[4]

Timeline

  1. Construction start3 Jan 2002
  2. Delivery29 Feb 2008

Significance

Pątnów II was the first unit with supercritical parameters in the national power system and one of the first large coal-fired units commissioned after years of stagnant investment in the Polish power sector. The 464 MW unit (474 MW rated capacity), fired with local lignite, substantially strengthened system stability in the central and northern part of the country and set the efficiency standard (44.0 per cent gross) for the supercritical units subsequently built in Poland (Łagisza, Bełchatów).

Sources 8 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. wnp.pl28 Feb 2008
    CostConstruction start
    Costkoszt jego budowy są oceniany jest na ok. 550 mln euro
    Construction startBudowa Pątnowa II trwała od 3 stycznia 2002 roku
  2. ZE PAK SA
  3. ZE PAK SA
  4. Energetykacieplna.pl5 Mar 2008
    StatusStageDelivery
    Status · Stage · DeliveryZE „PAK” SA, jako pierwszy w Polsce, oddał obecnie do ruchu nowoczesny blok energetyczny dużej mocy opalany węglem brunatnym
  5. Wikipedia (pl)
  6. cire.pl (Jacek Balcewicz)
    InvestorFunding
    Investorkonieczne było wyodrębnienie tzw. spółki celowej pod nazwą Elektrownia Pątnów II Sp. z o.o. Spółka powstała w lutym 2001 roku jako podmiot w 100 proc. zależny od ZE „PAK” SA.
    Fundingpodpisano także umowę kredytową z konsorcjum składającym się banków kanadyjskich oraz EBOR-u. Jej spłata nastąpi w ciągu 15 lat. Na dokończenie projektu Pątnów II PAK pożyczył od banków 222 mln EUR (plus 80 mln EURO kredytu odnawialnego na VAT i różnice kursowe)
    FundingPAK pożyczył od banków 222 mln EUR (plus 80 mln EURO kredytu odnawialnego na VAT i różnice kursowe), a od Narodowego Funduszu Ochrony Środowiska — 226 mln zł
    FundingElektrownia podpisała też wcześniej umowę pożyczki opiewającą na 90 mln EUR z jedną ze spółek z grupy POLSAT kontrolowanej przez Zygmunta Solorza – Żaka. Był to warunek postawiony przez bankowe konsorcjum
  7. eur-pln.pl2008
  8. Wikipedia (pl)
    Delivery
    DeliveryOficjalna data zakończenia budowy bloku i przekazania go do ruchu to 29 lutego 2008.